BILL NO A01244
SAME AS SAME AS S00699
SPONSOR Cahill (MS)
COSPNSR Colton, Moya, Rosenthal
MLTSPNSR
Amd S126, Pub Serv L
Provides that, prior to granting a certificate for the construction of an
electric transmission line facility, the public service commission must find
that the facility conforms to the most recent state energy plan and consider
whether approval of the facility would cause adverse impacts on the state's
environmental quality due to electric generation.Go to top