•  Summary 
  •  
  •  Actions 
  •  
  •  Floor Votes 
  •  
  •  Memo 
  •  
  •  Text 

S00980 Text:



 
                STATE OF NEW YORK
        ________________________________________________________________________
 
                                         980--A
 
                               2013-2014 Regular Sessions
 
                    IN SENATE
 
                                       (Prefiled)
 
                                     January 9, 2013
                                       ___________
 
        Introduced  by  Sens.  LIBOUS,  GRIFFO, HANNON -- read twice and ordered
          printed, and when printed to be committed to the Committee on  Finance
          --  recommitted  to the Committee on Finance in accordance with Senate
          Rule  6,  sec.  8  --  committee  discharged,  bill  amended,  ordered

          reprinted as amended and recommitted to said committee
 
        AN  ACT to amend the state finance law and the general municipal law, in
          relation to requiring full payment for delivered and accepted  materi-
          als pertaining to public work projects; and to amend the general busi-
          ness  law, in relation to prohibiting the retention of any payment due
          and owing a material supplier for a construction project
 
          The People of the State of New York, represented in Senate and  Assem-
        bly, do enact as follows:
 
     1    Section  1. Subdivisions 1 and 2 of section 139-f of the state finance
     2  law, subdivision 1 as added by chapter 769  of  the  laws  of  1978  and
     3  subdivision  2  as amended by section 16 of part MM of chapter 57 of the
     4  laws of 2008, are amended to read as follows:
     5    1. Payment by public owners to contractors. The contractor shall peri-

     6  odically, in accordance with the terms of the contract,  submit  to  the
     7  public owner and/or [his] its agent a requisition for a progress payment
     8  for  the  work  performed  and/or materials furnished to the date of the
     9  requisition, less any amount previously  paid  to  the  contractor.  The
    10  public  owner shall in accordance with the terms of the contract approve
    11  and promptly pay the requisition for the progress payment less an amount
    12  necessary to satisfy any claims, liens or judgments against the contrac-
    13  tor which have not been suitably discharged and less any retained amount
    14  as hereafter described. The public owner shall retain not more than five
    15  per centum of each progress payment, not including any payment for mate-
    16  rials pertinent to the project which have been delivered,  accepted  and

    17  are  covered  by  a  manufacturer's  warranty, and/or are graded to meet
    18  industry standards, to the contractor except that the public  owner  may
 
         EXPLANATION--Matter in italics (underscored) is new; matter in brackets
                              [ ] is old law to be omitted.
                                                                   LBD04256-03-4

        S. 980--A                           2
 
     1  retain  in excess of five per centum but not more than ten per centum of
     2  each progress payment, not including any payment for materials pertinent
     3  to the project which have been delivered, accepted and are covered by  a
     4  manufacturer's  warranty,  and/or are graded to meet industry standards,
     5  to the contractor provided that there are no requirements by the  public

     6  owner  for  the contractor to provide a performance bond and a labor and
     7  material bond both in the full amount of the contract. The public  owner
     8  shall pay in full, upon requisition from the contractor, for all materi-
     9  als  pertinent  to  the project which have been delivered to the site or
    10  off-site by the contractor and/or subcontractor and suitably stored  and
    11  secured  as  required  by the public owner and the contractor [provided,
    12  the public owner may limit such payment to  materials  in  short  and/or
    13  critical  supply and materials specially fabricated for the project each
    14  as defined in the contract]. When the work or major portions thereof  as
    15  contemplated  by  the terms of the contract are substantially completed,

    16  the contractor shall submit to the public owner and/or [his] its agent a
    17  requisition for payment of the remaining amount of the contract balance.
    18  Upon receipt of such requisition the  public  owner  shall  approve  and
    19  promptly pay the remaining amount of the contract balance less two times
    20  the value of any remaining items to be completed and an amount necessary
    21  to  satisfy  any claims, liens or judgments against the contractor which
    22  have not been suitably discharged. As the remaining items  of  work  are
    23  satisfactorily  completed  or corrected, the public owner shall promptly
    24  pay, upon receipt of a requisition, for these remaining  items  less  an
    25  amount  necessary  to satisfy any claims, liens or judgments against the
    26  contractor which have not been suitably discharged.  Any  claims,  liens
    27  and  judgments  referred to in this section shall pertain to the project

    28  and shall be filed in  accordance  with  the  terms  of  the  applicable
    29  contract and/or applicable laws.
    30    2.  Payment  by  contractors  to subcontractors. Within seven calendar
    31  days of the receipt of any payment from the public owner, the contractor
    32  shall pay each of [his] its subcontractors and materialmen the  proceeds
    33  from  the  payment  representing  the value of the work performed and/or
    34  materials furnished by the subcontractor and/or materialman and reflect-
    35  ing  the  percentage  of  the  subcontractor's  work  completed  or  the
    36  materialman's material supplied in the requisition approved by the owner
    37  and  based  upon  the  actual value of the subcontract or purchase order
    38  less an amount necessary to  satisfy  any  claims,  liens  or  judgments
    39  against  the  subcontractor  or materialman which have not been suitably

    40  discharged and, with regard to subcontractors, less any retained  amount
    41  as hereafter described. Failure by the contractor to pay any subcontrac-
    42  tor  or  materialman  within  seven  calendar days of the receipt of any
    43  payment from the public owner  shall  result  in  the  commencement  and
    44  accrual  of interest on amounts due to such subcontractor or materialman
    45  for the period beginning on the day immediately following the expiration
    46  of such seven calendar day period  and  ending  on  the  date  on  which
    47  payment  is made by the contractor to such subcontractor or materialman.
    48  Such interest payment shall be the sole responsibility of  the  contrac-
    49  tor,  and  shall  be  paid at the rate of interest in effect on the date
    50  payment is made by the contractor.  Notwithstanding any other  provision
    51  of  law  to  the contrary, interest shall be computed at the rate estab-

    52  lished in paragraph (b) of subdivision  one  of  section  seven  hundred
    53  fifty-six-b of the general business law. The contractor shall retain not
    54  more  than  five per centum of each payment to the subcontractor [and/or
    55  materialman] except that the contractor may retain in excess of five per
    56  centum but not more than ten per centum of each payment to  the  subcon-

        S. 980--A                           3
 
     1  tractor  provided  that  prior  to  entering into a subcontract with the
     2  contractor, the subcontractor  is  unable  or  unwilling  to  provide  a
     3  performance  bond and a labor and material bond, both in the full amount
     4  of  the  subcontract,  at the request of the contractor.  The contractor
     5  shall pay in full, upon payment by the public owner, for  all  materials

     6  pertinent  to  the  project which have been delivered to and accepted at
     7  the site or off-site by a materialman and are covered by  a  manufactur-
     8  er's  warranty,  and/or  are graded to meet industry standards. However,
     9  except in the case of a materialman who is also contracted to install  a
    10  product he/she delivered, the contractor shall retain nothing from those
    11  payments representing proceeds owed the subcontractor and/or materialman
    12  from  the  public  owner's  payments to the contractor for the remaining
    13  amounts of the contract balance as provided in subdivision one  of  this
    14  section.  If  the  contractor  has  failed  to  submit a requisition for
    15  payment of the remaining amounts of the contract balance  within  ninety
    16  days  of  substantial  completion as provided in subdivision one of this

    17  section, then any clause in the subcontract between the  contractor  and
    18  the  subcontractor  or  materialman  which  states  that  payment by the
    19  contractor to such  subcontractor  or  materialman  is  contingent  upon
    20  payment  by  the owner to the contractor shall be deemed invalid. Within
    21  seven calendar days of the receipt of payment from the  contractor,  the
    22  subcontractor and/or materialman shall pay each of [his] its subcontrac-
    23  tors  and  materialmen in the same manner as the contractor has paid the
    24  subcontractor, including interest  as  herein  provided  above.  Nothing
    25  provided  herein  shall  create any obligation on the part of the public
    26  owner to pay or to see to the payment of any moneys to any subcontractor
    27  or materialman from any contractor nor shall  anything  provided  herein
    28  serve  to  create  any relationship in contract or otherwise, implied or

    29  expressed, between the  subcontractor  or  materialman  and  the  public
    30  owner.
    31    § 2. Paragraph (a) of subdivision 1 and subdivision 2 of section 106-b
    32  of  the general municipal law, paragraph (a) of subdivision 1 as amended
    33  by chapter 98 of the laws of  1995  and  subdivision  2  as  amended  by
    34  section  15 of part MM of chapter 57 of the laws of 2008, are amended to
    35  read as follows:
    36    (a) The contractor shall periodically, in accordance with the terms of
    37  the contract, submit to the public owner and/or [his] its agent a requi-
    38  sition for a progress payment for the work  performed  and/or  materials
    39  furnished to the date of the requisition less any amount previously paid
    40  to  the  contractor. The public owner shall in accordance with the terms
    41  of the contract  approve  and  promptly  pay  the  requisition  for  the

    42  progress  payment  less an amount necessary to satisfy any claims, liens
    43  or judgments  against  the  contractor  which  have  not  been  suitably
    44  discharged  and  less  any  retained  amount as hereafter described. The
    45  public owner shall retain not more than five per centum of each progress
    46  payment, not including  any  payment  for  materials  pertinent  to  the
    47  project  which  have  been  delivered,  accepted  and  are  covered by a
    48  manufacturer's warranty, and/or are graded to meet  industry  standards,
    49  to  the  contractor except that the public owner may retain in excess of
    50  five per centum but not more  than  ten  per  centum  of  each  progress
    51  payment,  not  including  any  payment  for  materials  pertinent to the
    52  project which have  been  delivered,  accepted  and  are  covered  by  a

    53  manufacturer's  warranty,  and/or are graded to meet industry standards,
    54  to the contractor provided that there are no requirements by the  public
    55  owner  for  the contractor to provide a performance bond and a labor and
    56  material bond both in the full amount of the contract. The public  owner

        S. 980--A                           4
 
     1  shall pay in full, upon requisition from the contractor, for all materi-
     2  als  pertinent  to  the project which have been delivered to the site or
     3  off-site by the contractor and/or subcontractor and suitably stored  and
     4  secured  as  required  by the public owner and the contractor [provided,
     5  the public owner may limit such payment to  materials  in  short  and/or
     6  critical  supply and materials specially fabricated for the project each

     7  as defined in the contract]. When the work or major portions thereof  as
     8  contemplated  by  the terms of the contract are substantially completed,
     9  the contractor shall submit to the public owner and/or [his] its agent a
    10  requisition for payment of the remaining amount of the contract balance.
    11  Upon receipt of such requisition the  public  owner  shall  approve  and
    12  promptly pay the remaining amount of the contract balance less two times
    13  the value of any remaining items to be completed and an amount necessary
    14  to  satisfy  any claims, liens or judgments against the contractor which
    15  have not been suitably discharged. As the remaining items  of  work  are
    16  satisfactorily  completed  or corrected, the public owner shall promptly
    17  pay, upon receipt of a requisition,  for  these  items  less  an  amount

    18  necessary to satisfy any claims, liens or judgments against the contrac-
    19  tor which have not been suitably discharged. Any claims, liens and judg-
    20  ments referred to in this section shall pertain to the project and shall
    21  be  filed in accordance with the terms of the applicable contract and/or
    22  applicable laws. Where the public owner is other than the  city  of  New
    23  York,  the  term  "promptly  pay" shall mean payment within thirty days,
    24  excluding legal holidays, of receipt  of  the  requisition  unless  such
    25  requisition  is  not  approvable  in  accordance  with  the terms of the
    26  contract. Notwithstanding the foregoing, where the public owner is other
    27  than the city of New York and is a municipal corporation which  requires
    28  an  elected  official to approve progress payments, "promptly pay" shall
    29  mean payment  within  forty-five  days,  excluding  legal  holidays,  of

    30  receipt  of the requisition unless such requisition is not approvable in
    31  accordance with the terms of the contract.
    32    2. Payment by contractors to  subcontractors.  Within  seven  calendar
    33  days of the receipt of any payment from the public owner, the contractor
    34  shall  pay each of [his] its subcontractors and materialmen the proceeds
    35  from the payment representing the value of  the  work  performed  and/or
    36  materials furnished by the subcontractor and/or materialman and reflect-
    37  ing  the  percentage  of  the  subcontractor's  work  completed  or  the
    38  materialman's material supplied in the requisition approved by the owner
    39  and based upon the actual value of the  subcontract  or  purchase  order
    40  less  an  amount  necessary  to  satisfy  any claims, liens or judgments
    41  against the subcontractor or materialman which have  not  been  suitably

    42  discharged  and, with regard to subcontractors, less any retained amount
    43  as hereafter described. Failure by the contractor to make  any  payment,
    44  including  any  remaining amounts of the contract balance as hereinafter
    45  described, to any subcontractor or  materialman  within  seven  calendar
    46  days of the receipt of any payment from the public owner shall result in
    47  the  commencement and accrual of interest on amounts due to such subcon-
    48  tractor or materialman for the period beginning on the  day  immediately
    49  following the expiration of such seven calendar day period and ending on
    50  the  date on which payment is made by the contractor to such subcontrac-
    51  tor or materialman. Such interest shall be the  sole  responsibility  of
    52  the  contractor,  and shall be paid at the rate of interest in effect on
    53  the date payment is made by the contractor.  Notwithstanding  any  other

    54  provision of law to the contrary, interest shall be computed at the rate
    55  established in paragraph (b) of subdivision one of section seven hundred
    56  fifty-six-b of the general business law. The contractor shall retain not

        S. 980--A                           5
 
     1  more  than  five per centum of each payment to the subcontractor [and/or
     2  materialman] except that the contractor may retain in excess of five per
     3  centum but not more than ten per centum of each payment to  the  subcon-
     4  tractor  provided  that  prior  to  entering into a subcontract with the
     5  contractor, the subcontractor  is  unable  or  unwilling  to  provide  a
     6  performance  bond  and a labor and material bond both in the full amount
     7  of the subcontract at the request  of  the  contractor.  The  contractor

     8  shall  pay  in full, upon payment by the public owner, for all materials
     9  pertinent to the project which have been delivered to  and  accepted  at
    10  the  site  or off-site by a materialman and are covered by a manufactur-
    11  er's warranty, and/or are graded to meet  industry  standards.  However,
    12  except  in the case of a materialman who is also contracted to install a
    13  product he/she delivered, the contractor shall retain nothing from those
    14  payments representing proceeds owed the subcontractor and/or materialman
    15  from the public owner's payments to the  contractor  for  the  remaining
    16  amounts  of  the contract balance as provided in subdivision one of this
    17  section. If the contractor  has  failed  to  submit  a  requisition  for
    18  payment  of  the remaining amounts of the contract balance within ninety

    19  days of substantial completion as provided in subdivision  one  of  this
    20  section,  then  any clause in the subcontract between the contractor and
    21  the subcontractor or  materialman  which  states  that  payment  by  the
    22  contractor  to  such  subcontractor  or  materialman  is contingent upon
    23  payment by the owner to the contractor shall be deemed  invalid.  Within
    24  seven  calendar  days of the receipt of payment from the contractor, the
    25  subcontractor and/or materialman shall pay each of [his] its subcontrac-
    26  tors and materialmen in the same manner as the contractor has  paid  the
    27  subcontractor,  including  interest  as herein provided above.   Nothing
    28  provided herein shall create any obligation on the part  of  the  public
    29  owner to pay or to see to the payment of any moneys to any subcontractor
    30  or  materialman  from  any contractor nor shall anything provided herein

    31  serve to create any relationship in contract or  otherwise,  implied  or
    32  expressed,  between  the  subcontractor  or  materialman  and the public
    33  owner.
    34    § 3. Section 756-c of the general business law, as  added  by  chapter
    35  127 of the laws of 2002, is amended to read as follows:
    36    §  756-c. Retention. 1. By mutual agreement of the relevant parties an
    37  owner may retain a reasonable amount of the contract sum as retainage. A
    38  contractor or subcontractor may also  retain  a  reasonable  amount  for
    39  retainage  so  long  as the amount does not exceed the actual percentage
    40  retained by the owner. Retainage shall be released by the owner  to  the
    41  contractor  no  later  than  thirty days after the final approval of the
    42  work under a construction contract. In the event that an owner fails  to
    43  release  retainage  as  required  by  this article, or the contractor or

    44  subcontractor fails to release a proportionate amount  of  retainage  to
    45  the  relevant  parties  after  receipt  of retainage from the owner, the
    46  owner, contractor, or subcontractor,  as  the  case  may  be,  shall  be
    47  subject  to the payment of interest at the rate of one percent per month
    48  on the date retention was due and owing.
    49    2. Notwithstanding the provisions of subdivision one of this  section,
    50  no portion of any payment due and owing to a material supplier for mate-
    51  rials  which have been delivered, accepted and are covered by a manufac-
    52  turer's warranty, and/or graded to  meet  industry  standards  shall  be
    53  retained by an owner, contractor or subcontractor.
    54    §  4.  This  act shall take effect on the thirtieth day after it shall
    55  have become a law and shall apply to materials delivered and accepted on

    56  or after such effective date.
Go to top