A08800 Summary:

BILL NO    A08800 

SAME AS    SAME AS S06485

SPONSOR    Paulin

COSPNSR    Jaffee, Brindisi, Titone, Zebrowski, Gunther, Galef, Cahill, Crespo,
           Gottfried, Lupardo, Moya

MLTSPNSR   Cook, Magee, Rivera, Schimel, Schimminger, Skartados, Thiele

Amd S66-j, Pub Serv L

Changes the combined rated capacity of fuel cell electric generating equipment
for net energy metering for non-residential customers from 1,500 kilowatts to
2,000 kilowatts.
Go to top

A08800 Actions:

BILL NO    A08800 

02/14/2014 referred to energy
02/26/2014 reported referred to ways and means
05/19/2014 reported 
05/22/2014 advanced to third reading cal.772
05/29/2014 substituted by s6485
           S06485  AMEND=  MAZIARZ
           01/29/2014 REFERRED TO ENERGY AND TELECOMMUNICATIONS
           02/10/2014 1ST REPORT CAL.158
           02/11/2014 2ND REPORT CAL.
           02/26/2014 ADVANCED TO THIRD READING 
           03/04/2014 PASSED SENATE
           03/04/2014 DELIVERED TO ASSEMBLY
           03/04/2014 referred to ways and means
           05/29/2014 substituted for a8800
           05/29/2014 ordered to third reading cal.772
           05/29/2014 passed assembly
           05/29/2014 returned to senate
Go to top

A08800 Memo:

BILL NUMBER:A8800

TITLE OF BILL:  An act to amend the public service law, in relation to
fuel cell electric generating equipment

PURPOSE:

To allow non-residential customer generators who are utilizing net
metering for fuel cell electric generating equipment to install
systems of up to 2,000 kilowatts.

SUMMARY OF SPECIFIC PROVISIONS:

Section 1-amends section 66-J of the public service law to increase
the rated capacity of fuel cell electric generating equipment for
non-residential customers from 1500 kilowatts to 2000 kilowatts.

Section 2-Sets forth the effective date.

JUSTIFICATION:

Fuel cell- electric generating equipment for non-residential customers
was added to the technologies authorized to conduct net metering by
chapter 530 of the laws of 2011. However, this chapter placed the
upper limit in terms of rated capacity at 1500 kilowatts, which is
wholly inconsistent with other technologies that are authorized for
net metering. Therefore, this bill aims to level the playing field by
moving the upper rated capacity for fuel cells from 1500 kilowatts to
2000 kilowatts. This assures parity between fuel cells and other clean
energy technologies.

FISCAL IMPLICATIONS:

None

LEGISLATIVE HISTORY:

New Bill

EFFECTIVE DATE:

Immediately
Go to top

A08800 Text:

                           S T A T E   O F   N E W   Y O R K
       ________________________________________________________________________

                                         8800

                                 I N  A S S E M B L Y

                                   February 14, 2014
                                      ___________

       Introduced by M. of A. PAULIN -- read once and referred to the Committee
         on Energy

       AN  ACT  to amend the public service law, in relation to fuel cell elec-
         tric generating equipment

         THE PEOPLE OF THE STATE OF NEW YORK, REPRESENTED IN SENATE AND  ASSEM-
       BLY, DO ENACT AS FOLLOWS:

    1    Section  1.  Paragraph  (g)  of  subdivision  1 of section 66-j of the
    2  public service law, as amended by chapter 530 of the laws  of  2011,  is
    3  amended to read as follows:
    4    (g) "Fuel cell electric generating equipment" means:
    5    (i)(A)  in  the  case of a residential customer, a solid oxide, molten
    6  carbonate, proton exchange membrane or phosphoric acid fuel cell with  a
    7  combined  rated  capacity of not more than ten kilowatts; and (B) in the
    8  case of a non-residential customer, a  solid  oxide,  molten  carbonate,
    9  proton  exchange  membrane  or phosphoric acid fuel cell with a combined
   10  rated capacity of not more than [one] TWO thousand [five hundred]  kilo-
   11  watts; and
   12    (ii)  that  is manufactured, installed and operated in accordance with
   13  applicable government and industry standards, that is connected  to  the
   14  electric  system and operated in parallel with an electric corporation's
   15  transmission and  distribution  facilities,  and  that  is  operated  in
   16  compliance  with  any  standards and requirements established under this
   17  section.
   18    S 2. This act shall take effect immediately.




        EXPLANATION--Matter in ITALICS (underscored) is new; matter in brackets
                             [ ] is old law to be omitted.
                                                                  LBD13737-01-4
Go to top