A09472 Summary:

BILL NOA09472
 
SAME ASSAME AS S09086
 
SPONSORMagnarelli
 
COSPNSRMcDonald
 
MLTSPNSR
 
Add 66-x, Pub Serv L; amd 1005 & 1020-f, Pub Auth L
 
Requires the commissioner create rules, regulations, policies, and procedures for the creation of a resilient electric vehicle charging system pilot program to provide power through an extended outage.
Go to top

A09472 Text:



 
                STATE OF NEW YORK
        ________________________________________________________________________
 
                                          9472
 
                   IN ASSEMBLY
 
                                     March 14, 2024
                                       ___________
 
        Introduced  by  M.  of  A.  MAGNARELLI  -- read once and referred to the
          Committee on Energy
 
        AN ACT to amend the public service law and the public  authorities  law,
          in  relation  to creating a resilient electric vehicle charging system
          pilot program
 
          The People of the State of New York, represented in Senate and  Assem-
        bly, do enact as follows:

     1    Section  1.  The public service law is amended by adding a new section
     2  66-x to read as follows:
     3    § 66-x. Resilient electric vehicle charging system pilot program.   1.
     4  For the purposes of this section:
     5    (a)  "Resilient  carbon  free  power generation" shall mean only those
     6  generating stations which are:
     7    (i) manufactured, installed, and operated in accordance with  applica-
     8  ble government and industry standards;
     9    (ii) connected to the electric system and operated in conjunction with
    10  an electric corporation's transmission and distribution system;
    11    (iii)  operated  in  compliance  with  any  standards and requirements
    12  established under this section;
    13    (iv) utilize a synchronous  generator  with  black  start  capability,
    14  frequency control, and disconnect capability; and
    15    (v)  do  not  include  the  active use of fossil fuels and have a name
    16  plate capacity of 1.5 megawatts or less.
    17    (b) "Resilient electric vehicle charging system" shall mean  an  elec-
    18  tric  vehicle  (EV) microgrid designed to provide uninterrupted electric
    19  service for electric vehicle charging throughout an extended outage.
    20    (c) "Extended outage" shall mean an outage of  the  electric  distrib-
    21  ution system that continues for a period of twenty-four hours or longer.
    22    (d)  "Uninterrupted"  shall  mean  that the resilient electric vehicle
    23  charging system generates electricity  throughout  an  extended  outage,
    24  with  the  exception  of momentary interruptions associated with transi-
    25  tions to and from grid parallel and grid-islanded operations.
    26    (e) "EV microgrid" is a group of energy generating resources  with  at
    27  least  one  source  of resilient carbon free power generation and energy
 
         EXPLANATION--Matter in italics (underscored) is new; matter in brackets
                              [ ] is old law to be omitted.
                                                                   LBD14221-02-4

        A. 9472                             2
 
     1  storage within clearly defined electrical  boundaries  that  acts  as  a
     2  single  controllable  entity with respect to the grid for the purpose of
     3  electric vehicle charging and other emergency response needs  during  an
     4  extended  outage.  An  EV  microgrid can connect and disconnect from the
     5  grid to enable it to operate in both grid-connected or island-mode.
     6    2. The commissioner shall promulgate such rules, policies, and  proce-
     7  dures  necessary  and  appropriate no later than one hundred eighty days
     8  following the effective date of this section for:
     9    (a) creating  a  resilient  electric  vehicle  charging  system  pilot
    10  program  at  the  commercial  retail rate with a monthly cash out option
    11  program and a total program cap of 50 megawatts;
    12    (b) establishing a value stack adder for  valuation  of  uninterrupted
    13  resilient  carbon free power generation generated within an EV microgrid
    14  that is participating in the pilot program  that  supports  a  resilient
    15  electric vehicle charging system at the commercial retail rate; and
    16    (c)  creating  a  timely  interconnection process for resilient carbon
    17  free power generation comprising an EV microgrid.
    18    § 2. Section 1005 of the public authorities law is amended by adding a
    19  new subdivision 31 to read as follows:
    20    31. The authority in a manner consistent with section  sixty-six-x  of
    21  the  public  service  law,  shall  promulgate  such rules, policies, and
    22  procedures necessary and appropriate no later than  one  hundred  eighty
    23  days following the effective date of this subdivision for:
    24    (a)  creating  a  resilient  electric  vehicle  charging system at the
    25  commercial retail rate with a monthly cash  out  option  program  and  a
    26  total program cap of 50 megawatts;
    27    (b)  establishing  a  value stack adder for valuation of uninterrupted
    28  resilient carbon free power generation generated within an EV  microgrid
    29  that  is  also a participant of the pilot program that supports a resil-
    30  ient electric vehicle charging system at the commercial retail rate; and
    31    (c) creating a timely interconnection  process  for  resilient  carbon
    32  free power generation comprising an EV microgrid.
    33    § 3. Section 1020-f of the public authorities law, as added by chapter
    34  517  of the laws of 1986, is amended by adding a new subdivision (ll) to
    35  read as follows:
    36    (ll) The authority in a manner consistent with section sixty-six-x  of
    37  the  public  service  law,  shall  promulgate  such rules, policies, and
    38  procedures necessary and appropriate no later than  one  hundred  eighty
    39  days following the effective date of this section for:
    40    1.  creating  a  resilient  electric  vehicle  charging  system at the
    41  commercial retail rate with a monthly cash out option  program  and  the
    42  total program cap of 50 megawatts;
    43    2.  establishing  a  value  stack adder for valuation of uninterrupted
    44  resilient carbon free power generation generated within an EV  microgrid
    45  that  is  also a participant of the pilot program that supports a resil-
    46  ient electric vehicle charging system at the commercial retail rate; and
    47    3. creating a timely interconnection process for resilient carbon free
    48  power generation comprising an EV microgrid.
    49    § 4. This act shall take effect immediately.