A04386 Summary:

BILL NOA04386B
 
SAME ASSAME AS S00023-B
 
SPONSORO'Donnell
 
COSPNSREpstein, Dickens, Colton, Gottfried, Glick, Thiele, Abinanti, Lawler, Otis, Zebrowski, Stern, Englebright, Carroll, Lupardo, Simon
 
MLTSPNSR
 
Add 19-a, St Fin L
 
Requires the construction of certain parking facilities to be capable of supporting electric vehicle charging stations.
Go to top

A04386 Text:



 
                STATE OF NEW YORK
        ________________________________________________________________________
 
                                         4386--B
 
                               2021-2022 Regular Sessions
 
                   IN ASSEMBLY
 
                                    February 4, 2021
                                       ___________
 
        Introduced  by  M. of A. O'DONNELL, EPSTEIN, DICKENS, COLTON, GOTTFRIED,
          GLICK, THIELE, ABINANTI, LAWLER --  read  once  and  referred  to  the
          Committee  on  Governmental  Operations  -- committee discharged, bill
          amended, ordered reprinted as amended and recommitted to said  commit-
          tee  --  recommitted  to  the  Committee on Governmental Operations in
          accordance with Assembly Rule 3, sec. 2 -- committee discharged,  bill
          amended,  ordered reprinted as amended and recommitted to said commit-
          tee
 
        AN ACT to amend the state finance law,  in  relation  to  requiring  the
          construction of certain parking facilities to be capable of supporting
          electric vehicle charging stations
 
          The  People of the State of New York, represented in Senate and Assem-
        bly, do enact as follows:
 
     1    Section 1. The state finance law is amended by adding  a  new  section
     2  19-a to read as follows:
     3    §  19-a.  Parking  facilities;  support  for electric vehicle charging
     4  stations.   1. For purposes  of  this  section  the  term  "construction
     5  project"  shall  mean  any  construction project performed under private
     6  contract that receives state capital funding.
     7    2. Any construction project undertaken in this state where  the  scope
     8  of  such  project  includes a parking garage, open parking lot, or other
     9  parking facility that offers between fifty and two hundred parking spac-
    10  es shall be capable of supporting electric vehicle charging stations for
    11  a minimum of ten percent of available parking spaces  through  an  elec-
    12  trical raceway to the electric supply panel serving such parking garage,
    13  open  parking  lot,  or  other parking facility that shall be capable of
    14  providing a minimum of forty amps and two hundred eight volts  of  elec-
    15  trical  capacity to each charging station connected to the raceway. Such
    16  raceway and all components and work  appurtenant  thereto  shall  be  in
    17  accordance  with  all  applicable  state,  city and municipal electrical
    18  codes.
 
         EXPLANATION--Matter in italics (underscored) is new; matter in brackets
                              [ ] is old law to be omitted.
                                                                   LBD01758-06-2

        A. 4386--B                          2
 
     1    3. Any construction project undertaken in this state where  the  scope
     2  of  such  project  includes a parking garage, open parking lot, or other
     3  parking facility that offers more than two hundred parking spaces  shall
     4  be  capable of supporting electric vehicle charging stations for a mini-
     5  mum  of twenty percent of available parking spaces through an electrical
     6  raceway to the electric supply panel serving such parking  garage,  open
     7  parking  lot, or other parking facility that shall be capable of provid-
     8  ing a minimum of forty amps and two hundred eight  volts  of  electrical
     9  capacity to each charging station connected to the raceway. Such raceway
    10  and  all  components and work appurtenant thereto shall be in accordance
    11  with all applicable state, city and municipal electrical codes.
    12    4. Nothing in this section shall require the installation of  electric
    13  vehicle  charging  stations  in  any parking garage, open parking lot or
    14  other parking facility.
    15    5. Any construction project undertaken pursuant  to  subdivisions  two
    16  and  three  of  this section shall comply with the provisions of article
    17  eight of the labor law, including the payment of a wage of not less than
    18  the prevailing wage pursuant to section two hundred twenty of the  labor
    19  law  in  the  locality  where  such parking garage, open parking lot, or
    20  other parking facility is located.
    21    § 2. This act shall take effect April  1,  2023  and  shall  apply  to
    22  contracts for new construction entered into on and after such date.