S02378 Summary:

BILL NOS02378A
 
SAME ASSAME AS A01573-A
 
SPONSORPARKER
 
COSPNSR
 
MLTSPNSR
 
Amd §126, Pub Serv L
 
Provides that, prior to granting a certificate for the construction of an electric transmission line facility, the public service commission must find that the facility conforms to the most recent state energy plan and consider whether approval of the facility would cause adverse impacts on the state's environmental quality due to electric generation.