•  Summary 
  •  
  •  Actions 
  •  
  •  Committee Votes 
  •  
  •  Floor Votes 
  •  
  •  Memo 
  •  
  •  Text 
  •  
  •  LFIN 
  •  
  •  Chamber Video/Transcript 

A05344 Summary:

BILL NOA05344A
 
SAME ASSAME AS S05238-A
 
SPONSORCusick
 
COSPNSRPeoples-Stokes, D'Urso, Morinello, Santabarbara, Sepulveda, Colton, Bichotte
 
MLTSPNSR
 
Amd §139-f, St Fin L; amd §106-b, Gen Muni L
 
Provides for release of subcontractor's retainage held by a public owner or contractor sixty days after substantial completion of work.
Go to top

A05344 Memo:

NEW YORK STATE ASSEMBLY
MEMORANDUM IN SUPPORT OF LEGISLATION
submitted in accordance with Assembly Rule III, Sec 1(f)
 
BILL NUMBER: A5344A
 
SPONSOR: Cusick
  TITLE OF BILL: An act to amend the state finance law and the general municipal law, in relation to release of subcontractor's retainage   PURPOSE OR GENERAL IDEA OF BILL: This bill amends the general municipal law and the state finance law to provide for an early release of retainage on public jobs.   SUMMARY OF SPECIFIC PROVISIONS: Section 1 amends section 139-f (2) of the state finance law by adding the sentence, "Notwithstanding any other provision of this section or other law, any retainage held by a public owner or contractor represent- ing retainage for a subcontractor's work shall be released, less two times the value of any remaining items to be completed by the subcon- tractor and, no later than 60 days from the completion and acceptance by the public owner of the subcontractor's work." Section 2 amends section 106-b (2) of the general municipal law by adding the sentence, "Notwithstanding any other provision of this section or other law, any retainage held by a public owner or contractor representing retainage for a subcontractor's work shall be released, less two times the value of any remaining items to be completed by the subcontractor, and no later than 60 days from the completion and accept- ance by the public owner of the subcontractor's work."   JUSTIFICATION: Currently, subcontractors who have finished their work on a public job must wait until the entire project is complete before receiving their retainage. This creates hardships for subcontractors who must finance their work in advance and wait for unreasonably long periods of time for payment. Line item listing and early release of retainage will cure this unfairness and will insure subcontractor's payment within a reasonable time, thereby avoiding potential payment disputes and liens on the job.   PRIOR LEGISLATIVE HISTORY: 2016-215: A.4266 - Died in Assembly Governmental Operations/S.2924 - Passed Senate; 2013-2014: A.1660 - Died in Rules/ S.1974 - Passed Senate; 2012: A.5024 - Died in Assembly Governmental Operations; 2010: A.2372 - Died in Assembly Governmental Operations.   FISCAL IMPLICATIONS: None.   EFFECTIVE DATE: This act shall take effect immediately and shall apply to all contracts entered into on or after such effective date.
Go to top

A05344 Text:



 
                STATE OF NEW YORK
        ________________________________________________________________________
 
                                         5344--A
 
                               2017-2018 Regular Sessions
 
                   IN ASSEMBLY
 
                                    February 8, 2017
                                       ___________
 
        Introduced by M. of A. CUSICK, PEOPLES-STOKES, D'URSO, MORINELLO, SANTA-
          BARBARA,  SEPULVEDA, COLTON, BICHOTTE -- read once and referred to the
          Committee on Governmental Operations -- recommitted to  the  Committee
          on  Governmental Operations in accordance with Assembly Rule 3, sec. 2
          -- committee discharged, bill amended, ordered  reprinted  as  amended
          and recommitted to said committee
 
        AN  ACT to amend the state finance law and the general municipal law, in
          relation to release of subcontractor's retainage
 
          The People of the State of New York, represented in Senate and  Assem-
        bly, do enact as follows:
 
     1    Section 1. Subdivision 2 of section 139-f of the state finance law, as
     2  amended  by  section 16 of part MM of chapter 57 of the laws of 2008, is
     3  amended to read as follows:
     4    2. Payment by contractors to  subcontractors.  Within  seven  calendar
     5  days of the receipt of any payment from the public owner, the contractor
     6  shall  pay  each of his subcontractors and materialmen the proceeds from
     7  the payment representing the value of the work performed and/or  materi-
     8  als furnished by the subcontractor and/or materialman and reflecting the
     9  percentage  of  the  subcontractor's work completed or the materialman's
    10  material supplied in the requisition approved by  the  owner  and  based
    11  upon  the  actual  value  of  the  subcontract or purchase order less an
    12  amount necessary to satisfy any claims, liens or judgments  against  the
    13  subcontractor or materialman which have not been suitably discharged and
    14  less any retained amount as hereafter described. Failure by the contrac-
    15  tor  to  pay any subcontractor or materialman within seven calendar days
    16  of the receipt of any payment from the public owner shall result in  the
    17  commencement  and accrual of interest on amounts due to such subcontrac-
    18  tor or materialman for the  period  beginning  on  the  day  immediately
    19  following the expiration of such seven calendar day period and ending on
    20  the  date on which payment is made by the contractor to such subcontrac-
    21  tor or materialman. Such interest payment shall be the sole responsibil-
 
         EXPLANATION--Matter in italics (underscored) is new; matter in brackets
                              [ ] is old law to be omitted.
                                                                   LBD00257-02-7

        A. 5344--A                          2
 
     1  ity of the contractor, and shall be paid at  the  rate  of  interest  in
     2  effect  on  the date payment is made by the contractor.  Notwithstanding
     3  any other provision of law to the contrary, interest shall  be  computed
     4  at  the  rate established in paragraph (b) of subdivision one of section
     5  seven hundred fifty-six-b of the general business  law.  The  contractor
     6  shall  retain  not  more  than  five  per  centum of each payment to the
     7  subcontractor and/or materialman except that the contractor  may  retain
     8  in  excess  of  five per centum but not more than ten per centum of each
     9  payment to the subcontractor provided that  prior  to  entering  into  a
    10  subcontract  with the contractor, the subcontractor is unable or unwill-
    11  ing to provide a performance bond and a labor and material bond, both in
    12  the full amount of the subcontract, at the request  of  the  contractor.
    13  However, the contractor shall retain nothing from those payments repres-
    14  enting  proceeds  owed  the  subcontractor  and/or  materialman from the
    15  public owner's payments to the contractor for the remaining  amounts  of
    16  the  contract balance as provided in subdivision one of this section. If
    17  the contractor has failed to submit a requisition  for  payment  of  the
    18  remaining amounts of the contract balance within ninety days of substan-
    19  tial completion as provided in subdivision one of this section, then any
    20  clause  in  the subcontract between the contractor and the subcontractor
    21  or materialman which states that  payment  by  the  contractor  to  such
    22  subcontractor  or materialman is contingent upon payment by the owner to
    23  the contractor shall be deemed invalid. Within seven  calendar  days  of
    24  the  receipt  of  payment  from the contractor, the subcontractor and/or
    25  materialman shall pay each of his subcontractors and materialmen in  the
    26  same  manner  as  the  contractor  has paid the subcontractor, including
    27  interest as herein provided above. Nothing provided herein shall  create
    28  any  obligation  on the part of the public owner to pay or to see to the
    29  payment of any moneys to  any  subcontractor  or  materialman  from  any
    30  contractor  nor  shall  anything  provided  herein  serve  to create any
    31  relationship in contract or otherwise, implied or expressed, between the
    32  subcontractor or materialman and the public owner.  Notwithstanding  any
    33  other  provision  of  this section or other law, any retainage held by a
    34  public owner or contractor representing retainage for a  subcontractor's
    35  work  shall be released, less two times the value of any remaining items
    36  to be completed by the subcontractor and an amount necessary to  satisfy
    37  any  claims, liens or judgments against the subcontractor or materialman
    38  which have not been suitably discharged no later than  sixty  days  from
    39  the completion and acceptance by the public owner of the subcontractor's
    40  work.
    41    §  2.  Subdivision 2 of section 106-b of the general municipal law, as
    42  amended by section 15 of part MM of chapter 57 of the laws of  2008,  is
    43  amended to read as follows:
    44    2.  Payment  by  contractors  to subcontractors. Within seven calendar
    45  days of the receipt of any payment from the public owner, the contractor
    46  shall pay each of his subcontractors and materialmen the  proceeds  from
    47  the  payment representing the value of the work performed and/or materi-
    48  als furnished by the subcontractor and/or materialman and reflecting the
    49  percentage of the subcontractor's work completed  or  the  materialman's
    50  material  supplied  in  the  requisition approved by the owner and based
    51  upon the actual value of the  subcontract  or  purchase  order  less  an
    52  amount  necessary  to satisfy any claims, liens or judgments against the
    53  subcontractor or materialman which have not been suitably discharged and
    54  less any retained amount as hereafter described. Failure by the contrac-
    55  tor to make any payment, including any remaining amounts of the contract
    56  balance as hereinafter described, to any  subcontractor  or  materialman

        A. 5344--A                          3
 
     1  within seven calendar days of the receipt of any payment from the public
     2  owner  shall  result  in  the  commencement  and  accrual of interest on
     3  amounts due to such subcontractor or materialman for the  period  begin-
     4  ning  on  the  day  immediately  following  the expiration of such seven
     5  calendar day period and ending on the date on which payment is  made  by
     6  the contractor to such subcontractor or materialman. Such interest shall
     7  be  the  sole responsibility of the contractor, and shall be paid at the
     8  rate of interest in effect on the date payment is made by  the  contrac-
     9  tor.  Notwithstanding any other provision of law to the contrary, inter-
    10  est shall be computed at the rate established in paragraph (b) of subdi-
    11  vision one of section seven hundred fifty-six-b of the general  business
    12  law.  The  contractor shall retain not more than five per centum of each
    13  payment to the subcontractor and/or materialman except that the contrac-
    14  tor may retain in excess of five per centum but not more  than  ten  per
    15  centum  of  each  payment  to  the  subcontractor provided that prior to
    16  entering into a subcontract with the contractor,  the  subcontractor  is
    17  unable  or unwilling to provide a performance bond and a labor and mate-
    18  rial bond both in the full amount of the subcontract at the  request  of
    19  the  contractor. However, the contractor shall retain nothing from those
    20  payments representing proceeds owed the subcontractor and/or materialman
    21  from the public owner's payments to the  contractor  for  the  remaining
    22  amounts  of  the contract balance as provided in subdivision one of this
    23  section. If the contractor  has  failed  to  submit  a  requisition  for
    24  payment  of  the remaining amounts of the contract balance within ninety
    25  days of substantial completion as provided in subdivision  one  of  this
    26  section,  then  any clause in the subcontract between the contractor and
    27  the subcontractor or  materialman  which  states  that  payment  by  the
    28  contractor  to  such  subcontractor  or  materialman  is contingent upon
    29  payment by the owner to the contractor shall be deemed  invalid.  Within
    30  seven  calendar  days of the receipt of payment from the contractor, the
    31  subcontractor and/or materialman shall pay each  of  his  subcontractors
    32  and  materialmen  in  the  same  manner  as  the contractor has paid the
    33  subcontractor, including interest as herein  provided  above.    Nothing
    34  provided  herein  shall  create any obligation on the part of the public
    35  owner to pay or to see to the payment of any moneys to any subcontractor
    36  or materialman from any contractor nor shall  anything  provided  herein
    37  serve  to  create  any relationship in contract or otherwise, implied or
    38  expressed, between the  subcontractor  or  materialman  and  the  public
    39  owner.    Notwithstanding  any  other provision of this section or other
    40  law, any retainage held by a public  owner  or  contractor  representing
    41  retainage  for  a subcontractor's work shall be released, less two times
    42  the value of any remaining items to be completed  by  the  subcontractor
    43  and  an  amount  necessary  to  satisfy  any  claims, liens or judgments
    44  against the subcontractor or materialman which have  not  been  suitably
    45  discharged  no  later than sixty days from the completion and acceptance
    46  by the public owner of the subcontractor's work.
    47    § 3. This act shall take effect immediately and  shall  apply  to  all
    48  contracts entered into on or after such effective date.
Go to top