A09873 Summary:

BILL NOA09873
 
SAME ASSAME AS UNI. S06787
 
SPONSORCusick
 
COSPNSRCastro, Hyer-Spencer
 
MLTSPNSRHooper, McEneny, Reilly
 
Amd S139-f, St Fin L; amd S106-b, Gen Muni L
 
Provides that any contract change orders on a public work contract which exceeds the original contract or subcontract price shall be considered a new and separate project.
Go to top    

A09873 Actions:

BILL NOA09873
 
02/05/2010referred to governmental operations
Go to top

A09873 Floor Votes:

There are no votes for this bill in this legislative session.
Go to top

A09873 Text:



 
                STATE OF NEW YORK
        ________________________________________________________________________
 
            S. 6787                                                  A. 9873
 
                SENATE - ASSEMBLY
 
                                    February 5, 2010
                                       ___________
 
        IN SENATE -- Introduced by Sen. BRESLIN -- read twice and ordered print-
          ed, and when printed to be committed to the Committee on Finance
 
        IN  ASSEMBLY  -- Introduced by M. of A. CUSICK -- read once and referred
          to the Committee on Governmental Operations
 
        AN ACT to amend the state finance law and the general municipal law,  in
          relation to contract change orders
 

          The  People of the State of New York, represented in Senate and Assem-
        bly, do enact as follows:
 
     1    Section 1. Section 139-f of the state finance law is amended by adding
     2  a new subdivision 5 to read as follows:
     3    5. (a) If at any time during the construction period, the  total  cost
     4  of  all  change  orders, change directives and contract amendments shall
     5  exceed the original contract or subcontract price, such  excess  project
     6  work  shall  be  considered  a  new and separate project subject to this
     7  article.
     8    (b) If at any time during the construction period, the total  cost  of
     9  all  unapproved change orders, change directives and contract amendments
    10  exceeds ten  percent  of  the  original  contract  or  subcontract,  the

    11  contractor  or  subcontractor, as the case may be, shall not be required
    12  to commence or continue such work until the proposed changes  or  amend-
    13  ments have been approved by the public owner.
    14    § 2. Section 106-b of the general municipal law is amended by adding a
    15  new subdivision 4 to read as follows:
    16    4.  (a)  If at any time during the construction period, the total cost
    17  of all change orders, change directives and  contract  amendments  shall
    18  exceed  the  original contract or subcontract price, such excess project
    19  work shall be considered a new and  separate  project  subject  to  this
    20  article.
    21    (b)  If  at any time during the construction period, the total cost of
    22  all unapproved change orders, change directives and contract  amendments

    23  exceed ten percent of the original contract or subcontract, the contrac-
    24  tor  or  subcontractor,  as  the  case  may be, shall not be required to
 
         EXPLANATION--Matter in italics (underscored) is new; matter in brackets
                              [ ] is old law to be omitted.
                                                                   LBD15251-02-0

        S. 6787                             2                            A. 9873
 
     1  commence or continue such work until the proposed changes or  amendments
     2  have been approved by the public owner.
     3    §  3.  This  act  shall take effect immediately and shall apply to all
     4  contracts executed on and after the effective date of this act.