BILL NOA07098
 
SAME ASNo Same As
 
SPONSORBichotte Hermelyn
 
COSPNSRHyndman, Seawright, Walker
 
MLTSPNSR
 
Amd §139-f, St Fin L; amd §106-b, Gen Muni L
 
Relates to payment by public owners to contractors and subcontractors.
Go to top

A07098 Text:



 
                STATE OF NEW YORK
        ________________________________________________________________________
 
                                          7098
 
                               2025-2026 Regular Sessions
 
                   IN ASSEMBLY
 
                                     March 20, 2025
                                       ___________
 
        Introduced  by M. of A. BICHOTTE HERMELYN, HYNDMAN, SEAWRIGHT, WALKER --
          read once and referred to the Committee on Governmental Operations
 
        AN ACT to amend the state finance law and the general municipal law,  in
          relation to payment by public owners to contractors and subcontractors

          The  People of the State of New York, represented in Senate and Assem-
        bly, do enact as follows:
 
     1    Section 1. The opening paragraph and subdivisions 1 and 2  of  section
     2  139-f  of the state finance law, the opening paragraph as added by chap-
     3  ter 769 of the laws of 1978, subdivision 1 as amended by chapter 128  of
     4  the  laws  of 2021 and subdivision 2 as amended by section 16 of part MM
     5  of chapter 57 of the laws of 2008, are amended to read as follows:
     6    Notwithstanding the provisions of  any  other  law  to  the  contrary,
     7  except  the  provisions  of section thirty-eight of the highway law, all
     8  contracts made and awarded by the state, or by any public department, or
     9  by any public benefit corporation or by any public corporation or  offi-
    10  cial   thereof,   hereafter   referred  to  as  the  public  owner,  for
    11  construction, reconstruction or alteration of any  public  work  project
    12  shall  provide  for  payment  by  the public owner to the contractor and
    13  [payment by the contractor] to the subcontractor  or  subcontractors  in
    14  accordance with the following:
    15    1. Payment by public owners to contractors. The contractor shall peri-
    16  odically,  in  accordance  with the terms of the contract, submit to the
    17  public owner and/or [his] the public owner's agent a requisition  for  a
    18  progress  payment  for  the work performed and/or materials furnished to
    19  the date of the requisition by the contractor  and  all  subcontractors,
    20  less any amount previously paid to the contractor or subcontractors. The
    21  public  owner shall in accordance with the terms of the contract approve
    22  and promptly pay the requisition for the progress payment less an amount
    23  necessary to satisfy any claims, liens or judgments against the contrac-
    24  tor or subcontractors which have not been suitably discharged  and  less
    25  any  retained  amount  as  hereafter  described.  The public owner shall
 
         EXPLANATION--Matter in italics (underscored) is new; matter in brackets
                              [ ] is old law to be omitted.
                                                                   LBD10966-01-5

        A. 7098                             2
 
     1  retain not more than five per centum of each  progress  payment  to  the
     2  contractor  and  subcontractors, except that the public owner may retain
     3  in excess of five per centum but not more than ten per  centum  of  each
     4  progress  payment  to the contractor provided that there are no require-
     5  ments by the public owner for the contractor to  provide  a  performance
     6  bond  and  a  labor  and  material  bond  both in the full amount of the
     7  contract. The public owner shall pay, upon requisition from the contrac-
     8  tor, for materials pertinent to the project which have been delivered to
     9  the site or off-site by the contractor [and/or subcontractor] and  suit-
    10  ably stored and secured as required by the public owner and the contrac-
    11  tor  provided,  the  public owner may limit such payment to materials in
    12  short and/or critical supply and materials specially fabricated for  the
    13  project  each  as  defined  in  the contract, including balances owed to
    14  subcontractors. When the work or major portions thereof as  contemplated
    15  by the terms of the contract are substantially completed, the contractor
    16  shall submit to the public owner and/or [his] the public owner's agent a
    17  requisition for payment of the remaining amount of the contract balance.
    18  Upon  receipt  of  such  requisition  the public owner shall approve and
    19  promptly pay the remaining amount of the contract balance less two times
    20  the value of any remaining items to be completed and an amount necessary
    21  to satisfy any claims, liens or judgments against the  contractor  which
    22  have  not  been  suitably discharged. As the remaining items of work are
    23  satisfactorily completed or corrected, the public owner  shall  promptly
    24  pay,  upon  receipt  of a requisition, for these remaining items less an
    25  amount necessary to satisfy any claims, liens or judgments  against  the
    26  contractor  which  have  not been suitably discharged. Any claims, liens
    27  and judgments referred to in this section shall pertain to  the  project
    28  and  shall  be  filed  in  accordance  with  the terms of the applicable
    29  contract and/or applicable laws.
    30    2. Payment by [contractors] public owners to  subcontractors.  [Within
    31  seven calendar days of the receipt] (a) Each subcontractor shall period-
    32  ically,  in  accordance  with  the  terms of the contract, submit to the
    33  public owner and/or the public  owner's  agent  and  to  the  contractor
    34  and/or  the  contractor's agent a requisition for a progress payment for
    35  the work performed and/or materials furnished to the date of the  requi-
    36  sition,  less  any amount previously paid to the contractor. At the time
    37  of any payment [from] by  the  public  owner[,]  to  the  contractor  as
    38  provided  in subdivision one of this section, the public owner shall pay
    39  each of [his] the subcontractors and materialmen the proceeds  from  the
    40  payment  representing  the  value of the work performed and/or materials
    41  furnished by the subcontractor and/or  materialman  and  reflecting  the
    42  percentage  of  the  subcontractor's work completed or the materialman's
    43  material supplied in the requisition approved by  the  owner  and  based
    44  upon  the  actual  value  of  the  subcontract or purchase order less an
    45  amount necessary to satisfy any claims, liens or judgments  against  the
    46  subcontractor or materialman which have not been suitably discharged and
    47  less  any  retained  amount  as  hereafter  described.  [Failure  by the
    48  contractor to pay any subcontractor or materialman within seven calendar
    49  days of the receipt of any payment from the public owner shall result in
    50  the commencement and accrual of interest on amounts due to such  subcon-
    51  tractor  or  materialman for the period beginning on the day immediately
    52  following the expiration of such seven calendar day period and ending on
    53  the date on which payment is made by the contractor to such  subcontrac-
    54  tor or materialman. Such interest payment shall be the sole responsibil-
    55  ity  of  the  contractor,  and  shall be paid at the rate of interest in
    56  effect on the date payment is made by the contractor.    Notwithstanding

        A. 7098                             3

     1  any  other  provision of law to the contrary, interest shall be computed
     2  at the rate established in paragraph (b) of subdivision one  of  section
     3  seven  hundred  fifty-six-b  of the general business law. The contractor
     4  shall  retain  not  more  than  five  per  centum of each payment to the
     5  subcontractor and/or materialman except that the contractor  may  retain
     6  in  excess  of  five per centum but not more than ten per centum of each
     7  payment to the subcontractor provided that  prior  to  entering  into  a
     8  subcontract  with the contractor, the subcontractor is unable or unwill-
     9  ing to provide a performance bond and a labor and material bond, both in
    10  the full amount of the subcontract, at the request  of  the  contractor.
    11  However, the contractor shall retain nothing from those payments repres-
    12  enting  proceeds  owed  the  subcontractor  and/or  materialman from the
    13  public owner's payments to the contractor for the remaining  amounts  of
    14  the  contract balance as provided in subdivision one of this section. If
    15  the contractor has failed to submit a requisition  for  payment  of  the
    16  remaining amounts of the contract balance within ninety days of substan-
    17  tial completion as provided in subdivision one of this section, then any
    18  clause  in  the subcontract between the contractor and the subcontractor
    19  or materialman which states that  payment  by  the  contractor  to  such
    20  subcontractor  or materialman is contingent upon payment by the owner to
    21  the contractor shall be deemed invalid. Within seven  calendar  days  of
    22  the  receipt  of  payment  from the contractor, the subcontractor and/or
    23  materialman shall pay each of his subcontractors and materialmen in  the
    24  same  manner  as  the  contractor  has paid the subcontractor, including
    25  interest as herein provided above. Nothing provided herein shall  create
    26  any  obligation  on the part of the public owner to pay or to see to the
    27  payment of any moneys to  any  subcontractor  or  materialman  from  any
    28  contractor  nor  shall  anything  provided  herein  serve  to create any
    29  relationship in contract or otherwise, implied or expressed, between the
    30  subcontractor or materialman and the public owner.]   The  public  owner
    31  shall  retain  not more than five per centum of each progress payment to
    32  the subcontractor except that the public owner may retain in  excess  of
    33  five  per  centum  but  not  more  than  ten per centum of each progress
    34  payment to the subcontractor provided that there are no requirements  by
    35  the public owner for the subcontractor to provide a performance bond and
    36  a  labor  and material bond both in the full amount of the contract. The
    37  public owner shall pay, upon requisition from the contractor as provided
    38  in subdivision one of this  section,  for  materials  pertinent  to  the
    39  project which have been delivered to the site or off-site by the subcon-
    40  tractor  and suitably stored and secured as required by the public owner
    41  and the subcontractor provided, the public owner may limit such  payment
    42  to  materials  in  short  and/or critical supply and materials specially
    43  fabricated for the project each as defined in  the  contract.  When  the
    44  work  or  major  portions  thereof  as  contemplated by the terms of the
    45  contract are substantially completed, the subcontractor shall submit  to
    46  the  contractor  and/or the contractor's agent a requisition for payment
    47  of the remaining amount of the contract balance.  The  contractor  shall
    48  submit  a  contract requisition containing all requisitions from subcon-
    49  tractors to the public owner.  Upon  receipt  of  such  requisition  the
    50  public  owner shall approve and promptly pay the remaining amount of the
    51  contract balance less two times the value of any remaining items  to  be
    52  completed  and an amount necessary to satisfy any claims, liens or judg-
    53  ments against the subcontractor which have not been suitably discharged.
    54  As  the  remaining  items  of  work  are  satisfactorily  completed   or
    55  corrected, the public owner shall promptly pay, upon receipt of a requi-
    56  sition,  for  these  remaining items less an amount necessary to satisfy

        A. 7098                             4
 
     1  any claims, liens or judgments against the subcontractor which have  not
     2  been suitably discharged. Any claims, liens and judgments referred to in
     3  this  section shall pertain to the project and shall be filed in accord-
     4  ance with the terms of the applicable contract and/or applicable laws.
     5    (b)  As used in this section, "subcontractor" means only those subcon-
     6  tractors that report directly to  the  main  contractor  with  whom  the
     7  public owner has entered into the contract, and does not include subcon-
     8  tractors of subcontractors.
     9    §  2.  The opening paragraph and subdivisions 1 and 2 of section 106-b
    10  of the general municipal law, the opening paragraph as amended by  chap-
    11  ter  661 of the laws of 1992, subdivision 1 as amended by chapter 128 of
    12  the laws of 2021 and subdivision 2 as amended by section 15 of  part  MM
    13  of chapter 57 of the laws of 2008, are amended to read as follows:
    14    Notwithstanding  the  provisions of any other law to the contrary, all
    15  contracts made and awarded by the appropriate officer, board  or  agency
    16  of  a  political  subdivision  or  of  any  district  therein, hereafter
    17  referred to as the public owner,  for  construction,  reconstruction  or
    18  alteration  of  any public work project shall provide for payment by the
    19  public owner to the contractor and [payment by the  contractor]  to  the
    20  subcontractor or subcontractors in accordance with the following:
    21    1.  Payment  by public owners to contractors. (a) The contractor shall
    22  periodically, in accordance with the terms of the  contract,  submit  to
    23  the public owner and/or [his] the public owner's agent a requisition for
    24  a  progress payment for the work performed and/or materials furnished to
    25  the date of the requisition by the  contractor  and  all  subcontractors
    26  less any amount previously paid to the contractor or subcontractors. The
    27  public  owner shall in accordance with the terms of the contract approve
    28  and promptly pay the requisition for the progress payment less an amount
    29  necessary to satisfy any claims, liens or judgments against the contrac-
    30  tor or subcontractors which have not been suitably discharged  and  less
    31  any  retained  amount  as  hereafter  described.  The public owner shall
    32  retain not more than five per centum of each  progress  payment  to  the
    33  contractor  or subcontractors except that the public owner may retain in
    34  excess of five per centum but not more  than  ten  per  centum  of  each
    35  progress  payment  to the contractor provided that there are no require-
    36  ments by the public owner for the contractor to  provide  a  performance
    37  bond  and  a  labor  and  material  bond  both in the full amount of the
    38  contract. The public owner shall pay, upon requisition from the contrac-
    39  tor, for materials pertinent to the project which have been delivered to
    40  the site or off-site by the contractor [and/or subcontractor] and  suit-
    41  ably stored and secured as required by the public owner and the contrac-
    42  tor  provided,  the  public owner may limit such payment to materials in
    43  short and/or critical supply and materials specially fabricated for  the
    44  project each as defined in the contract. When the work or major portions
    45  thereof  as  contemplated by the terms of the contract are substantially
    46  completed, the contractor shall submit to the public owner and/or  [his]
    47  the  public  owner's  agent  a  requisition for payment of the remaining
    48  amount of the contract balance, including balances owed  to  subcontrac-
    49  tors.    Upon receipt of such requisition the public owner shall approve
    50  and promptly pay the remaining amount of the contract balance  less  two
    51  times  the  value  of  any remaining items to be completed and an amount
    52  necessary to satisfy any claims, liens or judgments against the contrac-
    53  tor which have not been suitably discharged. As the remaining  items  of
    54  work  are  satisfactorily completed or corrected, the public owner shall
    55  promptly pay, upon receipt of a requisition, for  these  items  less  an
    56  amount  necessary  to satisfy any claims, liens or judgments against the

        A. 7098                             5

     1  contractor which have not been suitably discharged.  Any  claims,  liens
     2  and  judgments  referred to in this section shall pertain to the project
     3  and shall be filed in  accordance  with  the  terms  of  the  applicable
     4  contract  and/or  applicable  laws. Where the public owner is other than
     5  the city of New York, the term "promptly pay" shall mean payment  within
     6  thirty  days,  excluding  legal  holidays, of receipt of the requisition
     7  unless such requisition is not approvable in accordance with  the  terms
     8  of  the  contract. Notwithstanding the foregoing, where the public owner
     9  is other than the city of New York and is a municipal corporation  which
    10  requires  an  elected  official  to approve progress payments, "promptly
    11  pay" shall mean payment within forty-five days,  excluding  legal  holi-
    12  days,  of  receipt  of  the  requisition  unless such requisition is not
    13  approvable in accordance with the terms of the contract.
    14    (b) Not later than forty-five business days after the  date  when  the
    15  project  has  reached substantial completion, as such term is defined in
    16  the contract or as it is contemplated by the terms of the contract,  the
    17  public  owner  shall  submit to the contractor a written list describing
    18  all remaining items to be completed by the contractor.  Not  later  than
    19  five business days after receiving a written list describing all remain-
    20  ing items to be completed by the contractor, the contractor shall submit
    21  to  each subcontractor from whom the contractor is withholding retainage
    22  a written list of all remaining items required to be  completed  by  the
    23  subcontractor. Such list may include items in addition to those items on
    24  the public owner's list.
    25    (c)  Each  public  owner  other  than  the  city  of New York which is
    26  required to make a payment from public funds pursuant to a contract  and
    27  which  does  not make such contract payment by the required payment date
    28  shall make an interest payment to the contractor on the  amount  of  the
    29  contract  payment  which  is  due  unless  failure to make such contract
    30  payment is the result of a lien,  attachment,  or  other  legal  process
    31  against  the  money  due  said  contractor,  or unless the amount of the
    32  interest payment as computed in accordance with the provisions set forth
    33  hereinafter is less than ten dollars. Interest payments on  amounts  due
    34  to a contractor pursuant to this paragraph shall be paid to the contrac-
    35  tor  for the period beginning on the day after the required payment date
    36  and ending on the payment date for those payments required according  to
    37  this  section and shall be paid at the rate of interest in effect on the
    38  date when the  interest  payment  is  made.  Notwithstanding  any  other
    39  provision of law to the contrary, interest shall be computed at the rate
    40  equal  to  the  overpayment rate set by the commissioner of taxation and
    41  finance pursuant to subsection (e) of section one thousand ninety-six of
    42  the tax law. A pro rata share of such interest  shall  be  paid  by  the
    43  contractor  or  subcontractor, as the case may be, to subcontractors and
    44  materialmen in a proportion equal to the percentage of  their  pro  rata
    45  share  of the contract payment. Such pro rata share of interest shall be
    46  due to such subcontractors and materialmen only for those payments which
    47  are not paid to such subcontractors and materialmen prior  to  the  date
    48  upon  which  interest  begins to accrue between the public owner and the
    49  contractor.  Such pro rata shares of interest shall  be  computed  daily
    50  until such payments are made to the subcontractors and materialmen.
    51    (d) For projects of a public owner other than the city of New York, if
    52  state  funds  directly  related  to and which have been budgeted for the
    53  construction of the project for which the payment is due have  not  been
    54  received prior to the expiration of the thirty or forty-five days speci-
    55  fied  in paragraph (a) of this subdivision, the interest provided for in
    56  paragraph (c) of this subdivision shall not begin to accrue and  payment

        A. 7098                             6
 
     1  shall not be due, until ten days after receipt of the state funds. Noth-
     2  ing  in this paragraph shall prevent the public owner from approving the
     3  requisition, subject to receipt of the state funds.  State  funds  shall
     4  mean  monies  provided  to  the public owner by the state, its officers,
     5  boards, departments, commissions, or a public authority and public bene-
     6  fit corporation, a majority of the members of which have been  appointed
     7  by  the  governor  or  who serve as members by virtue of holding a civil
     8  office of the state, or a combination thereof.
     9    2. Payment by [contractors] public owners to  subcontractors.  [Within
    10  seven calendar days of the receipt] (a) Each subcontractor shall period-
    11  ically,  in  accordance  with  the  terms of the contract, submit to the
    12  public owner and/or the public  owner's  agent  and  to  the  contractor
    13  and/or  the  contractor's agent a requisition for a progress payment for
    14  the work performed and/or materials furnished to the date of the  requi-
    15  sition,  less any amount previously paid to the contractor.  At the time
    16  of any payment [from] by  the  public  owner[,]  to  the  contractor  as
    17  provided  in subdivision one of this section, the public owner shall pay
    18  each of [his] the subcontractors and materialman the proceeds  from  the
    19  payment  representing  the  value of the work performed and/or materials
    20  furnished by the subcontractor and/or  materialmen  and  reflecting  the
    21  percentage  of  the  subcontractor's work completed or the materialmen's
    22  material supplied in the requisition approved by  the  owner  and  based
    23  upon  the  actual  value  of  the  subcontract or purchase order less an
    24  amount necessary to satisfy any claims, liens or judgments  against  the
    25  subcontractor or materialman which have not been suitably discharged and
    26  less  any  retained  amount  as  hereafter  described.  [Failure  by the
    27  contractor to make any payment, including any remaining amounts  of  the
    28  contract  balance  as  hereinafter  described,  to  any subcontractor or
    29  materialman within seven calendar days of the  receipt  of  any  payment
    30  from  the  public  owner shall result in the commencement and accrual of
    31  interest on amounts due to such subcontractor  or  materialman  for  the
    32  period beginning on the day immediately following the expiration of such
    33  seven  calendar  day  period  and ending on the date on which payment is
    34  made by the contractor to such subcontractor or materialman. Such inter-
    35  est shall be the sole responsibility of the  contractor,  and  shall  be
    36  paid  at  the  rate of interest in effect on the date payment is made by
    37  the contractor. Notwithstanding  any  other  provision  of  law  to  the
    38  contrary,  interest  shall  be computed at the rate established in para-
    39  graph (b) of subdivision one of section seven hundred fifty-six-b of the
    40  general business law. The contractor shall retain not more than five per
    41  centum of each payment to the subcontractor  and/or  materialman  except
    42  that the contractor may retain in excess of five per centum but not more
    43  than  ten  per centum of each payment to the subcontractor provided that
    44  prior to entering into a subcontract with the  contractor,  the  subcon-
    45  tractor is unable or unwilling to provide a performance bond and a labor
    46  and  material  bond  both  in  the full amount of the subcontract at the
    47  request of the contractor. However, the contractor shall retain  nothing
    48  from  those payments representing proceeds owed the subcontractor and/or
    49  materialman from the public owner's payments to the contractor  for  the
    50  remaining amounts of the contract balance as provided in subdivision one
    51  of  this  section.  If the contractor has failed to submit a requisition
    52  for payment of the remaining amounts  of  the  contract  balance  within
    53  ninety  days of substantial completion as provided in subdivision one of
    54  this section, then any clause in the subcontract between the  contractor
    55  and  the  subcontractor  or materialman which states that payment by the
    56  contractor to such  subcontractor  or  materialman  is  contingent  upon

        A. 7098                             7

     1  payment  by  the owner to the contractor shall be deemed invalid. Within
     2  seven calendar days of the receipt of payment from the  contractor,  the
     3  subcontractor  and/or  materialman  shall pay each of his subcontractors
     4  and  materialmen  in  the  same  manner  as  the contractor has paid the
     5  subcontractor, including interest as herein  provided  above.    Nothing
     6  provided  herein  shall  create any obligation on the part of the public
     7  owner to pay or to see to the payment of any moneys to any subcontractor
     8  or materialman from any contractor nor shall  anything  provided  herein
     9  serve  to  create  any relationship in contract or otherwise, implied or
    10  expressed, between the  subcontractor  or  materialman  and  the  public
    11  owner.]  The  public owner shall retain not more than five per centum of
    12  each progress payment to the subcontractor except that the public  owner
    13  may retain in excess of five per centum but not more than ten per centum
    14  of each progress payment to the subcontractor provided that there are no
    15  requirements  by  the  public  owner  for the subcontractor to provide a
    16  performance bond and a labor and material bond both in the  full  amount
    17  of  the  contract. The public owner shall pay, upon requisition from the
    18  contractor as provided in subdivision one of this section, for materials
    19  pertinent to the project which have been delivered to the site  or  off-
    20  site by the subcontractor and suitably stored and secured as required by
    21  the  public  owner  and the subcontractor provided, the public owner may
    22  limit such payment to materials in  short  and/or  critical  supply  and
    23  materials  specially  fabricated  for the project each as defined in the
    24  contract. When the work or major portions thereof as contemplated by the
    25  terms of the contract are  substantially  completed,  the  subcontractor
    26  shall  submit to the contractor and/or the contractor's agent a requisi-
    27  tion for payment of the remaining amount of the  contract  balance.  The
    28  contractor  shall  submit  a  contract requisition containing all requi-
    29  sitions from subcontractors to the public owner. Upon  receipt  of  such
    30  requisition  the public owner shall approve and promptly pay the remain-
    31  ing amount of the contract balance less  two  times  the  value  of  any
    32  remaining  items  to be completed and an amount necessary to satisfy any
    33  claims, liens or judgments against the subcontractor which have not been
    34  suitably discharged. As the remaining items of work  are  satisfactorily
    35  completed  or  corrected,  the  public  owner  shall  promptly pay, upon
    36  receipt of a requisition, for  these  remaining  items  less  an  amount
    37  necessary  to satisfy any claims, liens or judgments against the subcon-
    38  tractor which have not been suitably discharged. Any claims,  liens  and
    39  judgments  referred  to in this section shall pertain to the project and
    40  shall be filed in accordance with the terms of the  applicable  contract
    41  and/or applicable laws.
    42    (b)  As used in this section, "subcontractor" means only those subcon-
    43  tractors that report directly to  the  main  contractor  with  whom  the
    44  public owner has entered into the contract, and does not include subcon-
    45  tractors of subcontractors.
    46    §  3.  This  act shall take effect immediately.  Effective immediately
    47  the addition, amendment and/or repeal of any rule or  regulation  neces-
    48  sary  for  the  implementation  of  this  act  on its effective date are
    49  authorized to be made and completed on or before such date.
Go to top