•  Summary 
  •  
  •  Actions 
  •  
  •  Committee Votes 
  •  
  •  Floor Votes 
  •  
  •  Memo 
  •  
  •  Text 
  •  
  •  LFIN 
  •  
  •  Chamber Video/Transcript 

A11120 Summary:

BILL NOA11120
 
SAME ASSAME AS S08519
 
SPONSORKay
 
COSPNSR
 
MLTSPNSR
 
Amd §§3-c, 142 & 143, Pub Serv L
 
Relates to transparency and other requirements for applications submitted to ORES for siting of major renewable energy and major electric transmission facilities.
Go to top

A11120 Text:



 
                STATE OF NEW YORK
        ________________________________________________________________________
 
                                          11120
 
                   IN ASSEMBLY
 
                                     April 24, 2026
                                       ___________
 
        Introduced by M. of A. KAY -- read once and referred to the Committee on
          Corporations, Authorities and Commissions
 
        AN  ACT  to amend the public service law, in relation to certain reforms
          for ORES oversight of siting of major renewable energy facilities  and
          major electric transmission facilities
 
          The  People of the State of New York, represented in Senate and Assem-
        bly, do enact as follows:
 
     1    Section 1. Subdivision 2 of section 3-c of the public service  law  is
     2  amended by adding a new paragraph (g) to read as follows:
     3    (g)  ORES  shall  maintain  a  centralized, publicly accessible online
     4  dashboard that shall contain  up-to-date  information  on  all  projects
     5  pursuant  to  siting  permits pending or approved under article eight of
     6  this chapter. Such dashboard shall include, at a minimum, for each  such
     7  project:
     8    (i) name, location, and megawatt capacity;
     9    (ii) current status of such project;
    10    (iii) dates and status of all public comment periods and hearings;
    11    (iv) links to relevant public documents, including application materi-
    12  als, deficiency letters, responses, and determinations;
    13    (v) a summary of procedural milestones and anticipated timelines; and
    14    (vi)  a  tracker  for the status of applications submitted pursuant to
    15  subdivision one of section one hundred forty-two and subdivision one  of
    16  section  one  hundred  forty-three of this chapter, which shall include,
    17  but not be limited to:
    18    (1) the date of submission;
    19    (2) the date of determination of completeness; and
    20    (3) if applicable, any notices and communications between ORES and the
    21  applicant, including extensions of the time period for  a  determination
    22  of application completeness.
    23    § 2. Subdivisions 1, 5 and 6 of section 142 of the public service law,
    24  as  added by section 11 of part O of chapter 58 of the laws of 2024, are
    25  amended to read as follows:
    26    1. Notwithstanding any law to the contrary, ORES shall, within [sixty]
    27  ninety days of its receipt of an application for a  siting  permit  with
 
         EXPLANATION--Matter in italics (underscored) is new; matter in brackets
                              [ ] is old law to be omitted.
                                                                   LBD13519-04-5

        A. 11120                            2
 
     1  respect  to  a  major  renewable energy facility subject to this article
     2  determine whether the application is complete and notify  the  applicant
     3  of  its  determination.  If ORES does not deem the application complete,
     4  ORES  shall  set forth in writing delivered to the applicant the reasons
     5  why it has determined the application to be incomplete. If ORES fails to
     6  make a determination within the foregoing [sixty-day]  ninety  day  time
     7  period,  the  application  shall  be deemed complete; provided, however,
     8  that the applicant may consent to an extension of the [sixty-day] ninety
     9  day time period  for  determining  application  completeness.  Provided,
    10  further,  that no application may be complete without proof of consulta-
    11  tion with the municipality or political subdivision where the project is
    12  proposed to be located, or an agency thereof, prior to submission of  an
    13  application  to ORES, related to procedural and substantive requirements
    14  of local law.
    15    5. (a) Following the expiration of the public comment period set forth
    16  in this section, and following the conclusion of  a  hearing  undertaken
    17  pursuant to subdivision four of this section, ORES shall, in the case of
    18  a  public comment period, issue a written summary of public comments and
    19  an assessment of comments received, and in the case of  an  adjudicatory
    20  hearing,  the  executive  director  or  any person to whom the executive
    21  director has delegated such authority shall issue a final written  hear-
    22  ing  report.  A  final  siting permit may only be issued if ORES makes a
    23  finding that the proposed project, together with any applicable  uniform
    24  and site-specific standards and conditions, would comply with applicable
    25  laws and regulations. In making a final siting permit determination with
    26  respect  to  a  major  renewable  energy facility, ORES may elect not to
    27  apply, in whole or in part, any local law or ordinance that would other-
    28  wise be applicable if it  makes  a  finding  that,  as  applied  to  the
    29  proposed  facility,  it  is unreasonably burdensome in view of the CLCPA
    30  targets, and the environmental benefits.
    31    (b) ORES may find a local law or ordinance unreasonably burdensome  in
    32  view of the CLCPA targets and the environmental benefits under paragraph
    33  (a)  of  this  subdivision  only  if ORES makes a written determination,
    34  supported by substantial evidence, that:
    35    (i) such local law or ordinance would materially prevent  or  substan-
    36  tially  impair  the  state's  ability  to  meet its renewable energy and
    37  climate targets under the CLCPA; and
    38    (ii) the public health and safety objectives served by such local  law
    39  or  ordinance cannot be reasonably addressed through alternative project
    40  designs, site-specific permit conditions, or mitigation measures.
    41    (c) (i) If ORES determines to override a local law or ordinance  under
    42  this subdivision, the relevant municipality may request a public hearing
    43  on such determination. Such request shall be made within twenty business
    44  days  of  such  municipality's receipt of ORES's proposed findings under
    45  paragraph (b) of this subdivision.
    46    (ii) ORES shall respond to a request under subparagraph  (i)  of  this
    47  paragraph  within fourteen business days of receipt. ORES shall hold the
    48  requested public hearing unless  it  determines  in  writing  that  such
    49  public hearing request raises no material issues of fact or law.
    50    (iii)  After  holding a public hearing requested under this paragraph,
    51  or after denying the request for such public hearing, ORES  shall  issue
    52  final  written findings addressing each concern raised by the requesting
    53  municipality.
    54    6. (a) Notwithstanding any other  deadline  made  applicable  by  this
    55  section,  ORES  shall  make a final decision on a major renewable energy
    56  facility siting permit within one year from the date the application was

        A. 11120                            3
 
     1  deemed complete, or within six months from the date the application  was
     2  deemed  complete if such application relates to a major renewable energy
     3  facility that is proposed to  be  sited  on  an  existing  or  abandoned
     4  commercial  use,  including  without limitation, brownfields, landfills,
     5  former commercial  or  industrial  sites,  dormant  electric  generating
     6  sites,  and  abandoned  or  otherwise  underutilized  sites,  as further
     7  defined by the regulations promulgated by or in effect under this  arti-
     8  cle.  Unless ORES and the applicant have agreed to an extension and if a
     9  final siting permit decision has not been made by ORES within such  time
    10  period,  then  such  siting permit shall be deemed to have been automat-
    11  ically granted for all purposes  set  forth  in  this  article  and  all
    12  uniform  conditions  or  [site specific] site-specific permit conditions
    13  issued for public comment shall constitute enforceable provisions of the
    14  siting permit; provided, however, any portion of which is to be  located
    15  on  the  land  of  a landowner for which the applicant lacks an existing
    16  right-of-way agreement or valid and enforceable lease  or  easement  for
    17  use  of  such  relevant  property, no such permit shall be automatically
    18  granted. The final siting permit related to  a  major  renewable  energy
    19  facility  shall include a provision requiring the permittee to provide a
    20  host community benefit, which may be a host community benefit as  deter-
    21  mined by the commission pursuant to section eight of part JJJ of chapter
    22  fifty-eight  of the laws of two thousand twenty or such other project as
    23  determined by ORES or as subsequently agreed to  between  the  applicant
    24  and the host community.
    25    (b)  Where  uniform  conditions constitute enforceable provisions of a
    26  siting permit under paragraph (a) of this subdivision, if  such  uniform
    27  conditions override or preempt more protective local laws or ordinances,
    28  ORES shall provide a written explanation including:
    29    (i) why the local laws or ordinances cannot reasonably be met; and
    30    (ii) whether a tailored site-specific condition could achieve the same
    31  regulator objective.
    32    (c)  ORES shall expand its framework for uniform conditions as applied
    33  under paragraph (a) of this subdivision, to better  accommodate  locally
    34  significant concerns, including, but not limited to:
    35    (i) ground and surface water quality, and impact on wells; and
    36    (ii)  geological  concerns  including but not limited to seismic risk,
    37  soil stability and erosion, subsurface hydrogeology,  and  landslide  or
    38  subsidence risk.
    39    § 3. Subdivisions 7 and 8 of section 143 of the public service law, as
    40  added  by  section  11  of part O of chapter 58 of the laws of 2024, are
    41  amended to read as follows:
    42    7. (a) Following the expiration of the public comment period set forth
    43  in this section, and following the conclusion of  a  hearing  undertaken
    44  pursuant  to subdivision six of this section, ORES shall, in the case of
    45  a public comment period, issue a written summary of public comments  and
    46  an  assessment  of comments received, and in the case of an adjudicatory
    47  hearing, the executive officer or  any  person  to  whom  the  executive
    48  director  has delegated such authority shall issue a final written hear-
    49  ing report. A final siting permit may only be issued  if  ORES  makes  a
    50  finding  that the proposed project, together with any applicable uniform
    51  and site-specific standards and conditions, would comply with applicable
    52  laws and regulations. In making a final siting permit determination with
    53  respect to a major renewable energy facility or a major electric  trans-
    54  mission  facility, ORES may elect not to apply, in whole or in part, any
    55  local law or ordinance that would otherwise be applicable if it makes  a
    56  finding  that,  as  applied to the proposed facility, it is unreasonably

        A. 11120                            4
 
     1  burdensome in view of the CLCPA targets, the environmental benefits, and
     2  in the case of a transmission facility, the public need for the proposed
     3  project.
     4    (b)  ORES may find a local law or ordinance unreasonably burdensome in
     5  view of the CLCPA targets and the environmental benefits under paragraph
     6  (a) of this subdivision only if  ORES  makes  a  written  determination,
     7  supported by substantial evidence, that:
     8    (i)  such  local law or ordinance would materially prevent or substan-
     9  tially impair the state's ability  to  meet  its  renewable  energy  and
    10  climate targets under the CLCPA; and
    11    (ii)  the  public  health and safety served by such local law or ordi-
    12  nance  cannot  be  reasonably  addressed  through  alternative   project
    13  designs, site-specific permit conditions, or mitigation measures.
    14    (c)  (i) If ORES determines to override a local law or ordinance under
    15  this subdivision, the relevant municipality may request a public hearing
    16  on such determination. Such request shall be made within twenty business
    17  days of such municipality's receipt of ORES's  proposed  findings  under
    18  paragraph (b) of this subdivision.
    19    (ii)  ORES  shall  respond to a request under subparagraph (i) of this
    20  paragraph within fourteen business days of receipt. ORES shall hold  the
    21  requested  public  hearing  unless  it  determines  in writing that such
    22  public hearing request raises no material issues of fact or law.
    23    (iii) After holding a public hearing requested under  this  paragraph,
    24  or  after  denying the request for such public hearing, ORES shall issue
    25  final written findings addressing each concern raised by the  requesting
    26  municipality.
    27    8.  (a)  Notwithstanding  any  other  deadline made applicable by this
    28  section, ORES shall make a final decision on a siting permit within  one
    29  year  from the date the application was deemed complete. Unless ORES and
    30  the applicant have agreed to an extension and if a final  siting  permit
    31  decision  has  not  been made by ORES within such time period, then such
    32  siting permit shall be deemed to have been automatically granted for all
    33  purposes set forth in this article and all uniform conditions  or  [site
    34  specific]  site-specific  permit  conditions  issued  for public comment
    35  shall constitute enforceable provisions of the siting permit;  provided,
    36  however,  that with respect to a final siting permit decision related to
    37  a major electric transmission facility, any portion of which  is  to  be
    38  located  on  the  land  of  a landowner for which the applicant lacks an
    39  existing right-of-way agreement and in which ORES has not made a  public
    40  need determination, no such permit shall be automatically granted.
    41    (b)  Where  uniform  conditions constitute enforceable provisions of a
    42  siting permit under paragraph (a) of this subdivision, if  such  uniform
    43  conditions override or preempt more protective local laws or ordinances,
    44  ORES shall provide a written explanation including:
    45    (i) why the local laws or ordinances cannot reasonably be met; and
    46    (ii) whether a tailored site-specific condition could achieve the same
    47  regulator objective.
    48    (c)  ORES shall expand its framework for uniform conditions as applied
    49  under paragraph (a) of this subdivision, to better  accommodate  locally
    50  significant concerns, including, but not limited to:
    51    (i) ground and surface water quality, and impact on wells; and
    52    (ii)  geological  concerns  including but not limited to seismic risk,
    53  soil stability and erosion, subsurface hydrogeology,  and  landslide  or
    54  subsidence risk.
    55    §  4. Section 3-c of the public service law is amended by adding a new
    56  subdivision 3 to read as follows:

        A. 11120                            5
 
     1    3. For any public comment hearing operated by ORES:
     2    (a)  anyone  who  pre-registers  to  speak  during  the public comment
     3  portion shall be given at least two minutes to speak; and
     4    (b) the transcript of public comments shall be part of the administra-
     5  tive record.
     6    § 5. This act shall take effect on the one hundred eightieth day after
     7  it shall have become a law; provided, however that the  amendments  made
     8  to  sections 3-c, 142 and 143 of the public service law made by sections
     9  one, two, three and four of this act shall not affect the repeal of such
    10  sections and shall expire and be deemed  repealed  therewith.  Effective
    11  immediately,  the addition, amendment and/or repeal of any rule or regu-
    12  lation necessary for the implementation of this  act  on  its  effective
    13  date are authorized to be made and completed on or before such effective
    14  date.
Go to top