Add §66-i, Pub Serv L
 
Establishes a long-duration energy storage procurement target in New York state of three thousand megawatts by December thirty-first, two thousand thirty.
Go to top

A11402 Text:



 
                STATE OF NEW YORK
        ________________________________________________________________________
 
                                          11402
 
                   IN ASSEMBLY
 
                                      May 15, 2026
                                       ___________
 
        Introduced  by COMMITTEE ON RULES -- (at request of M. of A. Barrett) --
          read once and referred to the Committee on Energy
 
        AN ACT to amend the public service law, in relation  to  establishing  a
          long-duration energy storage procurement target in New York state
 
          The  People of the State of New York, represented in Senate and Assem-
        bly, do enact as follows:

     1    Section 1. The public service law is amended by adding a  new  section
     2  66-i to read as follows:
     3    §  66-i. Long-duration energy storage procurement target. 1.  Legisla-
     4  tive findings and declaration. The legislature finds and declares that:
     5    (a) Long-duration energy storage  ("LDES")  is  critical  to  enabling
     6  affordability  for  ratepayers,  maintaining  grid reliability, reducing
     7  system-wide costs, strengthening energy independence and economic devel-
     8  opment, supporting resilience to extreme weather events, and integrating
     9  renewable resources.
    10    (b) Achieving the state's clean energy goals at least cost,  including
    11  one  hundred  percent  zero-emission  electricity by two thousand forty,
    12  requires deployment of a portfolio of  energy  storage  technologies  of
    13  different durations.
    14    (c)  A  statewide  procurement target for LDES will provide regulatory
    15  certainty, encourage investment, and support the economic development of
    16  technologies that enable reliable, low-cost power.
    17    2. Definitions. As used in this section,  the  following  terms  shall
    18  have the following meanings:
    19    (a)  "Long-duration  energy  storage"  or "LDES" shall mean any energy
    20  storage system capable of storing and discharging electricity for ten or
    21  more hours at nameplate capacity,  including  both  inter-day  LDES  and
    22  multi-day LDES.
    23    (b)  "Inter-day  LDES" shall mean any energy storage system capable of
    24  storing and discharging electricity for a duration between ten and twen-
    25  ty-four hours at nameplate capacity.
    26    (c) "Multi-day LDES" shall mean any energy storage system  capable  of
    27  storing  and  discharging  electricity  for twenty-four or more hours at
    28  nameplate capacity.
 
         EXPLANATION--Matter in italics (underscored) is new; matter in brackets
                              [ ] is old law to be omitted.
                                                                   LBD15809-01-6

        A. 11402                            2
 
     1    (d) "Procurement target" shall mean the amount of incremental long-du-
     2  ration energy storage capacity contracted by the authority  pursuant  to
     3  this section.
     4    (e)  "Authority"  shall  mean  the  New York state energy research and
     5  development authority.
     6    3. Long-duration energy storage procurement target.  (a)  By  December
     7  thirty-first, two thousand thirty, the authority shall contract at least
     8  three  thousand  megawatts  of  incremental long-duration energy storage
     9  capacity, including at least one  thousand  five  hundred  megawatts  of
    10  inter-day  LDES  and  at  least  one  thousand five hundred megawatts of
    11  multi-day LDES.
    12    (b) No later than July first, two thousand twenty-seven,  the  commis-
    13  sion,  in consultation with the authority, shall publish an LDES roadmap
    14  that establishes a plan and timeline to achieve the  procurement  target
    15  established  pursuant  to this section. Such roadmap shall describe, but
    16  shall not be limited to, competitive solicitations, incentive  programs,
    17  or  other  procurement mechanisms to achieve the procurement target, and
    18  coordinate strategies with relevant agencies to ensure timely permitting
    19  and interconnection to achieve the procurement target.
    20    (c) The commission shall adopt one or  more  procurement  programs  to
    21  achieve  the  procurement  target  and  ensure  such program or programs
    22  commence no later than July first, two thousand twenty-eight.
    23    (d) The procurement target shall not limit any additional LDES deploy-
    24  ment beyond the required three thousand megawatts.
    25    § 2. This act shall take effect immediately.