S01227 Summary:

BILL NOS01227A
 
SAME ASSAME AS A04127-A
 
SPONSORMAY
 
COSPNSR
 
MLTSPNSR
 
 
Authorizes and directs the department of public service to conduct a study on the deployment of energy interconnection processes into the electrical grid to meet the state's renewable energy goals; directs the department of public service to submit a report on its findings one year after the effective date.
Go to top

S01227 Text:



 
                STATE OF NEW YORK
        ________________________________________________________________________
 
                                         1227--A
            Cal. No. 403
 
                               2025-2026 Regular Sessions
 
                    IN SENATE
 
                                     January 8, 2025
                                       ___________
 
        Introduced  by  Sen.  MAY  --  read  twice and ordered printed, and when
          printed to be committed to the Committee on  Energy  and  Telecommuni-
          cations  --  reported  favorably from said committee, ordered to first
          and second report, ordered to a third  reading,  amended  and  ordered
          reprinted, retaining its place in the order of third reading
 
        AN  ACT  to  authorize  and  direct  the department of public service to
          conduct a study on the deployment of energy interconnection  processes
          into the electrical grid
 
          The  People of the State of New York, represented in Senate and Assem-
        bly, do enact as follows:
 
     1    Section 1. Study. The department of public service is  authorized  and
     2  directed  to  conduct a study on the regulatory barriers, if any, to the
     3  rapid deployment of energy interconnection processes in the  state  that
     4  shall include, but not be limited to:
     5    (a)  Potential changes to the interconnection process to rapidly bring
     6  new renewable energy onto the electrical grid to meet the state's renew-
     7  able energy goals set out under the  climate  leadership  and  community
     8  protection act, as amended;
     9    (b)  The  state's  ability  to  comply  with  goals established in the
    10  climate leadership  and  community  protection  act,  as  amended,  with
    11  current  energy  interconnection process timelines, including the effect
    12  of recent reforms by the federally designated bulk system  operator  and
    13  any additional anticipated reforms;
    14    (c) The experience of other interconnection systems using "Connect and
    15  Manage" or other alternative connection agreements in terms of the speed
    16  of resource deployments and electrical grid reliability;
    17    (d)  The  extent  to  which the studies and network upgrades currently
    18  required for projects by the federally designated bulk  system  operator
    19  go  beyond  the  minimal  set  of studies and network upgrades needed to
    20  safely operate the system with a new resource;
 
         EXPLANATION--Matter in italics (underscored) is new; matter in brackets
                              [ ] is old law to be omitted.
                                                                   LBD03676-05-5

        S. 1227--A                          2
 
     1    (e) Whether it is possible to identify more efficient system  upgrades
     2  in the context of New York's federally designated bulk system operator's
     3  comprehensive  system  planning  process rather than certain studies and
     4  upgrades currently in the energy interconnection process;
     5    (f)  Improvements  to the interconnection process for qualified energy
     6  storage systems as defined by subdivision 1 of section 74 of the  public
     7  service law; and
     8    (g)  Whether  any changes identified in this study at the transmission
     9  level would also improve processes at the distribution level.
    10    § 2. Report. No later than one year after the effective date  of  this
    11  act,  the department of public service shall submit to the governor, the
    12  speaker of the assembly and the temporary president  of  the  senate,  a
    13  report  assessing  its  findings  under  the study conducted pursuant to
    14  section one of this act, and any recommendations to  rapidly  bring  new
    15  renewable  energy onto the electrical grid to meet the state's renewable
    16  energy  goals  set  out  under  the  climate  leadership  and  community
    17  protection act, as amended.
    18    §  3.  Definitions.  For the purposes of this act, the following terms
    19  shall have the following meanings:
    20    (a) "Energy interconnection process" means the process of  integrating
    21  new  sources  of  renewable  energy,  as  defined by section 66-p of the
    22  public service law, into the electrical grid.
    23    (b) "Electrical grid" means the network of electric plants  and  other
    24  electric  generating  facilities  and  equipment, and electricity trans-
    25  mission and distribution systems in the state.
    26    (c) "Renewable energy" shall have  the  same  meaning  as  defined  by
    27  section 66-p of the public service law.
    28    § 4. This act shall take effect immediately.