S01227 Summary:

BILL NOS01227
 
SAME ASSAME AS A04127
 
SPONSORMAY
 
COSPNSR
 
MLTSPNSR
 
 
Authorizes and directs the public service commission to conduct a study on the deployment of energy interconnection processes into the electrical grid to meet the state's renewable energy goals set out under the climate leadership and community protection act; directs the public service commission to submit a report on its findings one year after the effective date.
Go to top

S01227 Text:



 
                STATE OF NEW YORK
        ________________________________________________________________________
 
                                          1227
 
                               2025-2026 Regular Sessions
 
                    IN SENATE
 
                                     January 8, 2025
                                       ___________
 
        Introduced  by  Sen.  MAY  --  read  twice and ordered printed, and when
          printed to be committed to the Committee on  Energy  and  Telecommuni-
          cations
 
        AN  ACT to authorize and direct the public service commission to conduct
          a study on the deployment of energy interconnection processes into the
          electrical grid

          The People of the State of New York, represented in Senate and  Assem-
        bly, do enact as follows:
 
     1    Section  1.  Study.  The  public  service commission is authorized and
     2  directed to conduct a study on the regulatory barriers, if any,  to  the
     3  rapid  deployment  of energy interconnection processes in the state that
     4  shall include, but not be limited to:
     5    (a) Potential changes to the interconnection process to rapidly  bring
     6  new  renewable  energy  resources  onto  the electrical grid to meet the
     7  state's renewable energy goals set out under the climate leadership  and
     8  community protection act, as amended;
     9    (b)  The  state's  ability  to  comply  with  goals established in the
    10  climate leadership  and  community  protection  act,  as  amended,  with
    11  current  energy  interconnection process timelines, including the effect
    12  of recent reforms by the New York Independent System  Operator  and  any
    13  additional anticipated reforms;
    14    (c) The experience of other interconnection systems using "Connect and
    15  Manage" or other alternative connection agreements in terms of the speed
    16  of resource deployments and electrical grid reliability;
    17    (d)  The  extent  to  which the studies and network upgrades currently
    18  required for Energy Resource Interconnection Service projects in the New
    19  York Independent System Operator go beyond the minimal  set  of  studies
    20  and  network  upgrades  needed  to  safely operate the system with a new
    21  resource, in comparison to the United Kingdom's Enabling Works approach;
    22    (e) Whether it is possible to identify more efficient system  upgrades
    23  in the context of the New York Independent System Operator comprehensive

         EXPLANATION--Matter in italics (underscored) is new; matter in brackets
                              [ ] is old law to be omitted.
                                                                   LBD03676-01-5

        S. 1227                             2
 
     1  system  planning  process  rather  than  certain  studies  and  upgrades
     2  currently in the energy interconnection process;
     3    (f)  Whether  projects  that  initially  join  the  system with Energy
     4  Resource Interconnection Service status can be elevated to  the  Network
     5  Resource  Interconnection  Service  status  upon  completion of relevant
     6  network upgrades, to determine if there is a mechanism by which  genera-
     7  tors  could  be  allocated  part  of  the cost of such upgrades, if such
     8  upgrades are completed via the  comprehensive  system  planning  process
     9  rather than the energy interconnection process;
    10    (g)  Improvements  to the interconnection process for qualified energy
    11  storage systems as defined by subdivision 1 of section 74 of the  public
    12  service law; and
    13    (h)  Whether  any changes identified in this study at the transmission
    14  level would also improve processes at the distribution level.
    15    § 2. Report. No later than one year after the effective date  of  this
    16  act,  the  public  service  commission shall submit to the governor, the
    17  speaker of the assembly and the temporary president  of  the  senate,  a
    18  report  assessing  its  findings  under  the study conducted pursuant to
    19  section one of this act, and any recommendations to  rapidly  bring  new
    20  renewable  energy resources onto the electrical grid to meet the state's
    21  renewable energy goals set out under the climate leadership and communi-
    22  ty protection act, as amended.
    23    § 3. Definitions. For the purposes of this act,  the  following  terms
    24  shall have the following meanings:
    25    (a)  "Energy interconnection process" means the process of integrating
    26  new sources of renewable energy resources, as defined by  section  1-103
    27  of the energy law, into the electrical grid.
    28    (b)  "Electrical  grid" means the network of electric plants and other
    29  electric generating facilities and  equipment,  and  electricity  trans-
    30  mission and distribution systems in the state.
    31    (c)  "Renewable  energy  resources"  shall  have  the  same meaning as
    32  defined by section 1-103 of the energy law.
    33    § 4. This act shall take effect immediately.