S08349 Summary:

BILL NOS08349
 
SAME ASSAME AS A08560
 
SPONSORPALUMBO
 
COSPNSRMATTERA
 
MLTSPNSR
 
 
Directs the Department of Transportation to grant a permanent access and construction easement to the Metropolitan Transportation Authority for the use of a portion of DOT-owned land to support potential future rail yard development.
Go to top

S08349 Text:



 
                STATE OF NEW YORK
        ________________________________________________________________________
 
                                          8349
 
                               2025-2026 Regular Sessions
 
                    IN SENATE
 
                                      June 4, 2025
                                       ___________
 
        Introduced  by  Sen. PALUMBO -- read twice and ordered printed, and when
          printed to be committed to the Committee on Rules
 
        AN ACT in relation to directing  the  Department  of  Transportation  to
          grant a permanent access and construction easement to the Metropolitan
          Transportation Authority

          The  People of the State of New York, represented in Senate and Assem-
        bly, do enact as follows:
 
     1    Section 1. Short title. This act shall be known and may  be  cited  as
     2  the "Furthering Rail Transit in Suffolk County Act".
     3    § 2. Definitions. For the purposes of this act:
     4    (a) "DOT" means the New York State Department of Transportation.
     5    (b)  "Greenway"  means  the  real  property in Port Jefferson Station,
     6  Suffolk County, New York owned by  the  New  York  State  Department  of
     7  Transportation  identified as State Route 5232-A a/k/a the Setauket-Port
     8  Jefferson Station Greenway Multi-Use Path, which is bound on  the  north
     9  by   real   property  identified  on  the  Suffolk  County  Tax  Map  as
    10  0200-159.00-02.00-020.000 and bound on the south by real property  iden-
    11  tified on the Suffolk County Tax Map as 0200-180.00-04.00-002.000.
    12    (c) "MTA" means the Metropolitan Transportation Authority.
    13    § 3. Easement to MTA. (a) The DOT is hereby authorized and directed to
    14  grant  a  permanent access and construction easement to the MTA, in form
    15  and substance acceptable to the MTA, permitting the MTA  to  access  in,
    16  over, through and above, utilize, construct upon and operate, as needed,
    17  a  portion  of DOT-owned land identified as State Route 5232-A a/k/a the
    18  Setauket-Port Jefferson Station Greenway Multi-Use Path or  Greenway  to
    19  accommodate  the potential future development of a railyard use travers-
    20  ing the Greenway in order to expand and improve public rail  transit  in
    21  Suffolk County.
    22    (b) The DOT's grant of an easement over the Greenway, or such portions
    23  thereof  as  deemed  necessary by the MTA, shall reserve to the DOT such
    24  rights as may be required to construct a bridge over the current  Green-

         EXPLANATION--Matter in italics (underscored) is new; matter in brackets
                              [ ] is old law to be omitted.
                                                                   LBD13007-01-5

        S. 8349                             2
 
     1  way  location  in  order to carry out the intended purpose for which the
     2  Greenway was initially acquired by DOT, namely the straightening of  New
     3  York  State  Route  25A. The DOT's grant of an easement to the MTA shall
     4  include  language acknowledging that the MTA's potential future develop-
     5  ment of a railyard use and the DOT's potential future election to have a
     6  bridge constructed over the current Greenway location can coexist at the
     7  current Greenway location and requiring both parties  to  work  coopera-
     8  tively in the planning and construction phases so that in the event both
     9  projects are undertaken, they will coexist harmoniously.
    10    (c)  In  no event shall the easement prohibit the DOT's future ability
    11  to reroute the Greenway, which is presently being utilized as  a  pedes-
    12  trian  and  bicycle  path,  to  the parcel south of the current Greenway
    13  location or the DOT's future ability to opt to construct a  bridge  over
    14  the current Greenway location in order to carry out the intended purpose
    15  for  which the Greenway was initially acquired by DOT, the straightening
    16  of New York State Route 25A.
    17    (d) The DOT is authorized and directed to work with the MTA and  other
    18  interested parties and/or owners of real property surrounding the Green-
    19  way  to  negotiate  and  execute the above-described easement within six
    20  months after the effective date of this act.
    21    § 4. The DOT may consult with any state or local  office,  agency,  or
    22  department  and request or receive information from any such entity that
    23  is relevant and material to the completion of this directive to grant an
    24  easement to the MTA to accommodate the potential future development of a
    25  railyard use in order to expand  and  improve  public  rail  transit  in
    26  Suffolk County.
    27    § 5. This act shall take effect immediately.
Go to top