•  Summary 
  •  
  •  Actions 
  •  
  •  Committee Votes 
  •  
  •  Floor Votes 
  •  
  •  Memo 
  •  
  •  Text 
  •  
  •  LFIN 
  •  
  •  Chamber Video/Transcript 

S08519 Summary:

BILL NOS08519
 
SAME ASNo Same As
 
SPONSORMAY
 
COSPNSR
 
MLTSPNSR
 
Amd §§3-c, 142, 143 & 3-c, Pub Serv L
 
Relates to transparency and other requirements for applications submitted to ORES for siting of major renewable energy and major electric transmission facilities.
Go to top

S08519 Text:



 
                STATE OF NEW YORK
        ________________________________________________________________________
 
                                          8519
 
                               2025-2026 Regular Sessions
 
                    IN SENATE
 
                                     October 3, 2025
                                       ___________
 
        Introduced  by  Sen.  MAY  --  read  twice and ordered printed, and when
          printed to be committed to the Committee on Rules
 
        AN ACT to amend the public service law, in relation to  certain  reforms
          for  ORES oversight of siting of major renewable energy facilities and
          major electric transmission facilities

          The People of the State of New York, represented in Senate and  Assem-
        bly, do enact as follows:
 
     1    Section  1.  Subdivision 2 of section 3-c of the public service law is
     2  amended by adding a new paragraph (g) to read as follows:
     3    (g) ORES shall maintain  a  centralized,  publicly  accessible  online
     4  dashboard  that  shall  contain  up-to-date  information on all projects
     5  pursuant to siting permits pending or approved under  article  eight  of
     6  this  chapter. Such dashboard shall include, at a minimum, for each such
     7  project:
     8    (i) name, location, and megawatt capacity;
     9    (ii) current status of such project;
    10    (iii) dates and status of all public comment periods and hearings;
    11    (iv) links to relevant public documents, including application materi-
    12  als, deficiency letters, responses, and determinations;
    13    (v) a summary of procedural milestones and anticipated timelines; and
    14    (vi) a tracker for the status of applications  submitted  pursuant  to
    15  subdivision  one of section one hundred forty-two and subdivision one of
    16  section one hundred forty-three of this chapter,  which  shall  include,
    17  but not be limited to:
    18    (1) the date of submission;
    19    (2) the date of determination of completeness; and
    20    (3) if applicable, any notices and communications between ORES and the
    21  applicant,  including  extensions of the time period for a determination
    22  of application completeness.

         EXPLANATION--Matter in italics (underscored) is new; matter in brackets
                              [ ] is old law to be omitted.
                                                                   LBD13519-04-5

        S. 8519                             2
 
     1    § 2. Subdivisions 1, 5 and 6 of section 142 of the public service law,
     2  as added by section 11 of part O of chapter 58 of the laws of 2024,  are
     3  amended to read as follows:
     4    1. Notwithstanding any law to the contrary, ORES shall, within [sixty]
     5  ninety  days  of  its receipt of an application for a siting permit with
     6  respect to a major renewable energy facility  subject  to  this  article
     7  determine  whether  the application is complete and notify the applicant
     8  of its determination. If ORES does not deem  the  application  complete,
     9  ORES  shall  set forth in writing delivered to the applicant the reasons
    10  why it has determined the application to be incomplete. If ORES fails to
    11  make a determination within the foregoing [sixty-day]  ninety  day  time
    12  period,  the  application  shall  be deemed complete; provided, however,
    13  that the applicant may consent to an extension of the [sixty-day] ninety
    14  day time period  for  determining  application  completeness.  Provided,
    15  further,  that no application may be complete without proof of consulta-
    16  tion with the municipality or political subdivision where the project is
    17  proposed to be located, or an agency thereof, prior to submission of  an
    18  application  to ORES, related to procedural and substantive requirements
    19  of local law.
    20    5. (a) Following the expiration of the public comment period set forth
    21  in this section, and following the conclusion of  a  hearing  undertaken
    22  pursuant to subdivision four of this section, ORES shall, in the case of
    23  a  public comment period, issue a written summary of public comments and
    24  an assessment of comments received, and in the case of  an  adjudicatory
    25  hearing,  the  executive  director  or  any person to whom the executive
    26  director has delegated such authority shall issue a final written  hear-
    27  ing  report.  A  final  siting permit may only be issued if ORES makes a
    28  finding that the proposed project, together with any applicable  uniform
    29  and site-specific standards and conditions, would comply with applicable
    30  laws and regulations. In making a final siting permit determination with
    31  respect  to  a  major  renewable  energy facility, ORES may elect not to
    32  apply, in whole or in part, any local law or ordinance that would other-
    33  wise be applicable if it  makes  a  finding  that,  as  applied  to  the
    34  proposed  facility,  it  is unreasonably burdensome in view of the CLCPA
    35  targets, and the environmental benefits.
    36    (b) ORES may find a local law or ordinance unreasonably burdensome  in
    37  view of the CLCPA targets and the environmental benefits under paragraph
    38  (a)  of  this  subdivision  only  if ORES makes a written determination,
    39  supported by substantial evidence, that:
    40    (i) such local law or ordinance would materially prevent  or  substan-
    41  tially  impair  the  state's  ability  to  meet its renewable energy and
    42  climate targets under the CLCPA; and
    43    (ii) the public health and safety objectives served by such local  law
    44  or  ordinance cannot be reasonably addressed through alternative project
    45  designs, site-specific permit conditions, or mitigation measures.
    46    (c) (i) If ORES determines to override a local law or ordinance  under
    47  this subdivision, the relevant municipality may request a public hearing
    48  on such determination. Such request shall be made within twenty business
    49  days  of  such  municipality's receipt of ORES's proposed findings under
    50  paragraph (b) of this subdivision.
    51    (ii) ORES shall respond to a request under subparagraph  (i)  of  this
    52  paragraph  within fourteen business days of receipt. ORES shall hold the
    53  requested public hearing unless  it  determines  in  writing  that  such
    54  public hearing request raises no material issues of fact or law.
    55    (iii)  After  holding a public hearing requested under this paragraph,
    56  or after denying the request for such public hearing, ORES  shall  issue

        S. 8519                             3
 
     1  final  written findings addressing each concern raised by the requesting
     2  municipality.
     3    6.  (a)  Notwithstanding  any  other  deadline made applicable by this
     4  section, ORES shall make a final decision on a  major  renewable  energy
     5  facility siting permit within one year from the date the application was
     6  deemed  complete, or within six months from the date the application was
     7  deemed complete if such application relates to a major renewable  energy
     8  facility  that  is  proposed  to  be  sited  on an existing or abandoned
     9  commercial use, including without  limitation,  brownfields,  landfills,
    10  former  commercial  or  industrial  sites,  dormant  electric generating
    11  sites, and  abandoned  or  otherwise  underutilized  sites,  as  further
    12  defined  by the regulations promulgated by or in effect under this arti-
    13  cle. Unless ORES and the applicant have agreed to an extension and if  a
    14  final  siting permit decision has not been made by ORES within such time
    15  period, then such siting permit shall be deemed to  have  been  automat-
    16  ically  granted  for  all  purposes  set  forth  in this article and all
    17  uniform conditions or [site specific]  site-specific  permit  conditions
    18  issued for public comment shall constitute enforceable provisions of the
    19  siting  permit; provided, however, any portion of which is to be located
    20  on the land of a landowner for which the  applicant  lacks  an  existing
    21  right-of-way  agreement  or  valid and enforceable lease or easement for
    22  use of such relevant property, no such  permit  shall  be  automatically
    23  granted.  The  final  siting  permit related to a major renewable energy
    24  facility shall include a provision requiring the permittee to provide  a
    25  host  community benefit, which may be a host community benefit as deter-
    26  mined by the commission pursuant to section eight of part JJJ of chapter
    27  fifty-eight of the laws of two thousand twenty or such other project  as
    28  determined  by  ORES  or as subsequently agreed to between the applicant
    29  and the host community.
    30    (b) Where uniform conditions constitute enforceable  provisions  of  a
    31  siting  permit  under paragraph (a) of this subdivision, if such uniform
    32  conditions override or preempt more protective local laws or ordinances,
    33  ORES shall provide a written explanation including:
    34    (i) why the local laws or ordinances cannot reasonably be met; and
    35    (ii) whether a tailored site-specific condition could achieve the same
    36  regulator objective.
    37    (c) ORES shall expand its framework for uniform conditions as  applied
    38  under  paragraph  (a) of this subdivision, to better accommodate locally
    39  significant concerns, including, but not limited to:
    40    (i) ground and surface water quality, and impact on wells; and
    41    (ii) geological concerns including but not limited  to  seismic  risk,
    42  soil  stability  and  erosion, subsurface hydrogeology, and landslide or
    43  subsidence risk.
    44    § 3. Subdivisions 7 and 8 of section 143 of the public service law, as
    45  added by section 11 of part O of chapter 58 of the  laws  of  2024,  are
    46  amended to read as follows:
    47    7. (a) Following the expiration of the public comment period set forth
    48  in  this  section,  and following the conclusion of a hearing undertaken
    49  pursuant to subdivision six of this section, ORES shall, in the case  of
    50  a  public comment period, issue a written summary of public comments and
    51  an assessment of comments received, and in the case of  an  adjudicatory
    52  hearing,  the  executive  officer  or  any  person to whom the executive
    53  director has delegated such authority shall issue a final written  hear-
    54  ing  report.  A  final  siting permit may only be issued if ORES makes a
    55  finding that the proposed project, together with any applicable  uniform
    56  and site-specific standards and conditions, would comply with applicable

        S. 8519                             4
 
     1  laws and regulations. In making a final siting permit determination with
     2  respect  to a major renewable energy facility or a major electric trans-
     3  mission facility, ORES may elect not to apply, in whole or in part,  any
     4  local  law or ordinance that would otherwise be applicable if it makes a
     5  finding that, as applied to the proposed facility,  it  is  unreasonably
     6  burdensome in view of the CLCPA targets, the environmental benefits, and
     7  in the case of a transmission facility, the public need for the proposed
     8  project.
     9    (b)  ORES may find a local law or ordinance unreasonably burdensome in
    10  view of the CLCPA targets and the environmental benefits under paragraph
    11  (a) of this subdivision only if  ORES  makes  a  written  determination,
    12  supported by substantial evidence, that:
    13    (i)  such  local law or ordinance would materially prevent or substan-
    14  tially impair the state's ability  to  meet  its  renewable  energy  and
    15  climate targets under the CLCPA; and
    16    (ii)  the  public  health and safety served by such local law or ordi-
    17  nance  cannot  be  reasonably  addressed  through  alternative   project
    18  designs, site-specific permit conditions, or mitigation measures.
    19    (c)  (i) If ORES determines to override a local law or ordinance under
    20  this subdivision, the relevant municipality may request a public hearing
    21  on such determination. Such request shall be made within twenty business
    22  days of such municipality's receipt of ORES's  proposed  findings  under
    23  paragraph (b) of this subdivision.
    24    (ii)  ORES  shall  respond to a request under subparagraph (i) of this
    25  paragraph within fourteen business days of receipt. ORES shall hold  the
    26  requested  public  hearing  unless  it  determines  in writing that such
    27  public hearing request raises no material issues of fact or law.
    28    (iii) After holding a public hearing requested under  this  paragraph,
    29  or  after  denying the request for such public hearing, ORES shall issue
    30  final written findings addressing each concern raised by the  requesting
    31  municipality.
    32    8.  (a)  Notwithstanding  any  other  deadline made applicable by this
    33  section, ORES shall make a final decision on a siting permit within  one
    34  year  from the date the application was deemed complete. Unless ORES and
    35  the applicant have agreed to an extension and if a final  siting  permit
    36  decision  has  not  been made by ORES within such time period, then such
    37  siting permit shall be deemed to have been automatically granted for all
    38  purposes set forth in this article and all uniform conditions  or  [site
    39  specific]  site-specific  permit  conditions  issued  for public comment
    40  shall constitute enforceable provisions of the siting permit;  provided,
    41  however,  that with respect to a final siting permit decision related to
    42  a major electric transmission facility, any portion of which  is  to  be
    43  located  on  the  land  of  a landowner for which the applicant lacks an
    44  existing right-of-way agreement and in which ORES has not made a  public
    45  need determination, no such permit shall be automatically granted.
    46    (b)  Where  uniform  conditions constitute enforceable provisions of a
    47  siting permit under paragraph (a) of this subdivision, if  such  uniform
    48  conditions override or preempt more protective local laws or ordinances,
    49  ORES shall provide a written explanation including:
    50    (i) why the local laws or ordinances cannot reasonably be met; and
    51    (ii) whether a tailored site-specific condition could achieve the same
    52  regulator objective.
    53    (c)  ORES shall expand its framework for uniform conditions as applied
    54  under paragraph (a) of this subdivision, to better  accommodate  locally
    55  significant concerns, including, but not limited to:
    56    (i) ground and surface water quality, and impact on wells; and

        S. 8519                             5

     1    (ii)  geological  concerns  including but not limited to seismic risk,
     2  soil stability and erosion, subsurface hydrogeology,  and  landslide  or
     3  subsidence risk.
     4    §  4. Section 3-c of the public service law is amended by adding a new
     5  subdivision 3 to read as follows:
     6    3. For any public comment hearing operated by ORES:
     7    (a) anyone who  pre-registers  to  speak  during  the  public  comment
     8  portion shall be given at least two minutes to speak; and
     9    (b) the transcript of public comments shall be part of the administra-
    10  tive record.
    11    § 5. This act shall take effect on the one hundred eightieth day after
    12  it  shall  have become a law; provided, however that the amendments made
    13  to sections 3-c, 142 and 143 of the public service law made by  sections
    14  one, two, three and four of this act shall not affect the repeal of such
    15  sections  and  shall  expire and be deemed repealed therewith. Effective
    16  immediately, the addition, amendment and/or repeal of any rule or  regu-
    17  lation  necessary  for  the  implementation of this act on its effective
    18  date are authorized to be made and completed on or before such effective
    19  date.
Go to top