S09500 Summary:

BILL NOS09500
 
SAME ASSAME AS A10354
 
SPONSORHINCHEY
 
COSPNSR
 
MLTSPNSR
 
Add Art 12 §§240 - 244, Pub Serv L
 
Establishes the New York State grid reliability and energy affordability transition (GREAT) act; establishes the virtual power plant program to help reduce energy costs and grid reliability risks; provides incentives to participants for supporting the grid by investing in distributed energy resources and reducing net energy costs.
Go to top

S09500 Text:



 
                STATE OF NEW YORK
        ________________________________________________________________________
 
                                          9500
 
                    IN SENATE
 
                                     March 18, 2026
                                       ___________
 
        Introduced  by  Sen. HINCHEY -- read twice and ordered printed, and when
          printed to be committed to the Committee on  Energy  and  Telecommuni-
          cations
 
        AN  ACT to amend the public service law, in relation to establishing the
          New York State grid reliability and  energy  affordability  transition
          act
 
          The  People of the State of New York, represented in Senate and Assem-
        bly, do enact as follows:
 
     1    Section 1. This act shall be known and may be cited as the  "New  York
     2  State grid reliability and energy affordability transition (GREAT) act".
     3    §  2. Legislative findings and declarations. The legislature finds and
     4  declares that:
     5    1. New Yorkers face rising energy costs  and  grid  reliability  risks
     6  driven  by  extreme weather, aging infrastructure, and use of expensive,
     7  polluting fossil fuel plants to meet peak demand.
     8    2. A virtual power plant is a coordinated network of energy  resources
     9  like batteries, electric vehicles, and smart thermostats working togeth-
    10  er  to  help meet the needs of the electric grid. During periods of peak
    11  demand for electricity, virtual power plants can reduce  demand,  supply
    12  electricity,  and  provide  other  essential  grid  services, preventing
    13  blackouts and lessening the need for costly upgrades to utility  infras-
    14  tructure.
    15    3.  Virtual  power  plants can lower electric bills for all ratepayers
    16  and reduce emissions of greenhouse gases and other air pollutants, espe-
    17  cially from aging "peaker plants" in disadvantaged communities.  Virtual
    18  power plants also pay participating families and businesses for support-
    19  ing  the  grid,  enabling  and encouraging them to invest in distributed
    20  energy resources and reduce their net energy costs. This  can  help  the
    21  state  advance its clean energy goals and give customers tools to better
    22  manage their energy bills.
    23    4. Current market rules, complex energy program structures, and inade-
    24  quate compensation to participants are preventing New  York  from  using
    25  virtual  power  plants at the scale they are capable of, leaving a great

         EXPLANATION--Matter in italics (underscored) is new; matter in brackets
                              [ ] is old law to be omitted.
                                                                   LBD14809-02-6

        S. 9500                             2
 
     1  potential source of grid reliability,  ratepayer  savings  and  customer
     2  benefits untapped.
     3    5.  Through  the  Reforming  the  Energy Vision initiative, the Public
     4  Service Commission has taken  important  steps  toward  modernizing  New
     5  York's  energy  system,  encouraging  utilities to work proactively with
     6  customers and third-party providers to start the integration of distrib-
     7  uted energy resources into system planning and operations  in  order  to
     8  lower  system  costs,  reduce  emissions, meet clean energy targets, and
     9  advance other public policy goals.  Through  this  act  the  legislature
    10  provides  comprehensive  guidance  to strengthen, accelerate, and codify
    11  those efforts, giving the Commission clear statutory direction to expand
    12  distributed energy markets by enhancing existing utility  programs,  and
    13  providing  new  program  opportunities.  This  act  further  directs the
    14  Commission to reduce program  barriers  and  maximize  the  benefits  of
    15  virtual power plants.
    16    6.  The  policy  of  New  York State shall therefore be to establish a
    17  statewide virtual power plant program to promote greater use of distrib-
    18  uted energy resources to support a cleaner, more affordable,  resilient,
    19  and reliable electric grid.
    20    §  3.  The public service law is amended by adding a new article 12 to
    21  read as follows:
    22                                 ARTICLE 12
    23                         VIRTUAL POWER PLANT PROGRAM
    24  Section 240. Definitions.
    25          241. Virtual power plant program.
    26          242. Cost recovery.
    27          243. Program targets and performance incentive mechanisms.
    28          244. Reporting.
    29    § 240. Definitions. Where used in this article, the  following  terms,
    30  unless  the  context  otherwise requires, shall have the following mean-
    31  ings:
    32    1. "Aggregator" means a person or entity, other than a utility or  its
    33  affiliate, that enrolls and manages customer participation in the virtu-
    34  al  power  plant program. An aggregator shall not be considered an elec-
    35  tric corporation by virtue of its participation in the program.
    36    2. "Battery" means a commercially available non-electric vehicle ener-
    37  gy storage system utilizing mechanical, chemical or thermal processes to
    38  absorb energy generated at one period of time, store such energy  for  a
    39  period of time, and discharge it for use at a later time.
    40    3.  "Battery  rider"  means  the  section of a utility's virtual power
    41  plant program tariff that specifies the terms and conditions for battery
    42  resource participation.
    43    4. "Capacity value" refers to the value  from  reducing  energy  usage
    44  during the most energy-intensive days of the year.
    45    5.  "Demand  reduction  value"  means  the  monetary  value of avoided
    46  distribution system costs.
    47    6. "Demand response" means actions taken by a customer to  reduce  the
    48  amount of electric load supplied by a utility, including through reduced
    49  customer  consumption  or  the  use of controllable water heaters, smart
    50  thermostats and other non-battery technologies.
    51    7. "Direct participant" means a customer that enrolls in  the  virtual
    52  power  plant program directly with a utility rather than via an aggrega-
    53  tor.
    54    8. "Disadvantaged community" means a community identified as disadvan-
    55  taged pursuant to the criteria set forth in section 75-0111 of the envi-
    56  ronmental conservation law.

        S. 9500                             3
 
     1    9. "Distributed energy resource" means batteries, non-battery technol-
     2  ogies, and electric vehicles that are capable of  reducing  or  shifting
     3  customer  load  supplied  by  a utility, generating electricity, storing
     4  electricity, and/or discharging electricity to  supply  customer  energy
     5  needs and/or export it to the grid.
     6    10.  "Electric  vehicle"  means a car, truck, bus or other mobile unit
     7  that utilizes electric power stored in an onboard battery for propulsion
     8  along with the associated equipment utilized to charge the battery.
     9    11. "Electric vehicle rider" means the section of a utility's  virtual
    10  power  plant  program tariff that specifies the terms and conditions for
    11  electric vehicle resource participation.
    12    12. "Eligible customer" means an active residential or  small  commer-
    13  cial  electric  service  account  holder  of  a utility with an eligible
    14  device.
    15    13. "Eligible device" means customer or third-party-owned  distributed
    16  energy  resources that meet the requirements for participation specified
    17  in the relevant virtual power plant program rider.
    18    14. "Grid event" means a condition on an electric system  in  response
    19  to  which  a  utility calls upon a virtual power plant to provide a grid
    20  service.
    21    15. "Grid service" means those services identified in paragraph (a) of
    22  subdivision one of section two hundred forty-one of this article.
    23    16. "Locational system relief  value"  means  the  monetary  value  of
    24  avoided distribution costs in specific geographic locations.
    25    17.  "Low-to-moderate  income customer" means a utility account holder
    26  for a household with an income of up to  eighty  percent  of  the  state
    27  median income or area median income, whichever is greater.
    28    18.  "Non-battery technology" means demand response and customer-sited
    29  devices, including but not limited to smart thermostats, water  heaters,
    30  and  other  devices that can be controlled to reduce or otherwise modify
    31  customer energy consumption.
    32    19. "Non-battery rider" means the section of a utility's virtual power
    33  plant program tariff that specifies the terms and  conditions  for  non-
    34  battery resource participation.
    35    20. "Participant" means an aggregator or a direct participant.
    36    21. "Performance payment" means the compensation received by a partic-
    37  ipant  for  the  amount of grid service delivered or deemed delivered by
    38  the customer, device or aggregator during the applicable grid  event  or
    39  grid events.
    40    22.  "Program rider" means one or more of the following: (a) a battery
    41  rider; (b) a non-battery rider; (c) an electric vehicle  rider;  or  (d)
    42  any other virtual power plant program rider approved by the commission.
    43    23.  "System  peak  load  reduction"  means a reduction in electricity
    44  demand or the amount of electricity supplied by  a  utility  during  the
    45  highest use periods of the day.
    46    24.  "Utility" means an electric corporation as defined in section two
    47  of this chapter.
    48    25. "Utilization factor" means a system or device's capacity used at a
    49  particular time as a percentage of the system or device's total  capaci-
    50  ty.
    51    26.  "Value of distributed energy resources" means a structured frame-
    52  work  for  determining  the  component  values  of  distributed   energy
    53  resources  established  by  the  commission  in  Case  15-E-0751, or any
    54  successor proceeding.
    55    27. "Virtual power plant" means an aggregation of  distributed  energy
    56  resources operated in coordination to provide one or more grid services.

        S. 9500                             4
 
     1    28. "Virtual power plant program tariff" or "tariff" means the commis-
     2  sion  approved standardized terms and conditions, including formal pric-
     3  ing schedules and operating rules,  governing  aggregator  and  customer
     4  participation and utility operation of the virtual power plant program.
     5    § 241. Virtual power plant program. 1. No later than ninety days after
     6  the  effective  date  of  this article, each utility shall file with the
     7  commission a virtual power plant  program  proposal  including  standard
     8  terms  and  conditions  for participation and compensation in accordance
     9  with the requirements of this  article.  Each  utility  shall  post  its
    10  proposal  in  a  conspicuous and easily accessible place on its website.
    11  The commission shall provide public notice of each  utility's  proposal,
    12  assign  a case number in the commission's document and matter management
    13  system, provide opportunity for the public and parties to  the  case  to
    14  comment for a period of not less than sixty days, and provide such other
    15  opportunity  for  public input as the commission determines appropriate.
    16  The commission shall conduct at least two public hearings on each utili-
    17  ty's proposal following the public comment period. Public hearings shall
    18  be held within the utility's service territory, at least  one  of  which
    19  shall  be  held  in a disadvantaged community within such territory, and
    20  shall offer video participation and any other  measures  the  commission
    21  deems appropriate to ensure accessibility. Within ninety days of a util-
    22  ity  filing  its  proposal, the commission shall, after consideration of
    23  all public and party comments, approve, or approve  with  modifications,
    24  the virtual power plant program. Within thirty days of final approval by
    25  the  commission,  the  utility  shall file a virtual power plant program
    26  tariff proposal with the commission for program implementation. No later
    27  than forty-five days after  a  utility  files  a  tariff  proposal,  the
    28  commission  shall  approve,  or  approve with modification, the proposed
    29  tariff for immediate implementation. Upon  such  approval,  the  utility
    30  shall  update  its  website  with the final approved program and provide
    31  additional customer education materials and such other  content  as  the
    32  commission  may  direct  or  approve  on its website. Such materials and
    33  other content shall be distributed through bill inserts and  such  other
    34  means deemed appropriate by the commission to sufficiently educate rate-
    35  payers of the program's existence, benefits, and how to participate.
    36    (a)  The  program  filed  pursuant to this subdivision shall include a
    37  battery rider and a non-battery rider, and may include a separate  elec-
    38  tric  vehicle  rider  for  eligible customers to enroll eligible devices
    39  into the applicable rider for their respective technologies. Each  rider
    40  shall  independently, at a minimum, provide a system peak load reduction
    41  service offering, and may provide  additional  grid  service  offerings,
    42  including, but not limited to:
    43    (i)  clean  peak  service to reduce reliance on fossil fuel generation
    44  during peak demand periods;
    45    (ii)  congestion  relief,  system  utilization   factor   improvement,
    46  location   specific   demand  reduction,  and  other  location  specific
    47  services;
    48    (iii) avoidance or deferral of need to construct new or upgrade exist-
    49  ing components of the distribution system;
    50    (iv) ancillary services, including but not limited to voltage  support
    51  and frequency regulation; and
    52    (v) such other grid services as the commission may direct or otherwise
    53  deem are in the public interest.
    54    (b) The program filed pursuant to this subdivision shall provide oper-
    55  ating  parameters  and related terms for each grid service offered under
    56  each technology specific rider, which shall include:

        S. 9500                             5
 
     1    (i) the minimum and maximum numbers of grid  events  the  utility  may
     2  call;
     3    (ii) the months of the year that grid events may occur;
     4    (iii) days of the week that grid events may occur;
     5    (iv) times of day that grid events may occur;
     6    (v) maximum duration of grid events;
     7    (vi) day-ahead notification of grid events, along with ability to call
     8  events  on  a day-of basis for grid services or grid events that are not
     9  or cannot be forecasted on a day-ahead basis;
    10    (vii) a list of eligible devices; and
    11    (viii) such other provisions as the commission may direct or otherwise
    12  deem appropriate.
    13    (c) If a utility does not include an electric vehicle rider as part of
    14  the utility's initial filing pursuant to this subdivision, such  utility
    15  shall file for commission approval of such rider no later than two years
    16  after the effective date of this article.
    17    (i) The electric vehicle rider shall, at a minimum:
    18    (1)  offer  opportunities  for  program participants to provide system
    19  peak load reduction services. The rider may also offer opportunities  to
    20  provide  additional  grid  services  identified in paragraph (a) of this
    21  subdivision.
    22    (2) address the parameters identified in paragraph (b) of this  subdi-
    23  vision for each grid service offering.
    24    (3)  be  posted  by the utility in a conspicuous and easily accessible
    25  place on the utility's website.
    26    (ii) The commission shall provide  public  notice  of  each  utility's
    27  electric  vehicle rider proposal and assign a case number in the commis-
    28  sion's document and matter management system. The provisions  and  time-
    29  frames for commission approvals and for implementation provided in para-
    30  graph (a) of this subdivision shall apply to the electric vehicle rider,
    31  except that the public hearing requirement shall be waived.
    32    (d)  On  an  annual  basis on such date as directed by the commission,
    33  each utility shall file a report identifying any grid service listed  in
    34  paragraph (b) of this subdivision that is not included as a grid service
    35  offering  for  any  rider  then in effect. Each report shall discuss any
    36  grid conditions, technology constraints or other circumstances  prevent-
    37  ing  the  utility from including such grid service offerings and provide
    38  an assessment of what conditions or circumstances would need  to  be  in
    39  place  to  incorporate  such  offerings  in  the respective riders. Such
    40  reports shall be subject to comment by the parties to the rider and  the
    41  public.    The  commission may direct utilities to submit for commission
    42  approval additional grid service offerings under one or more  riders  as
    43  the commission deems appropriate.
    44    2. The virtual power plant program, inclusive of the respective riders
    45  filed  pursuant  to  subdivision  one of this section, shall include the
    46  following additional terms and conditions:
    47    (a) Provisions for the participation  of  aggregators,  including  the
    48  ability  to directly enroll, unenroll and otherwise manage their custom-
    49  ers' participation, receive dispatch  instructions  and  other  communi-
    50  cations from the utility, and receive program payments directly from the
    51  utility.
    52    (b)  Provisions for direct participant customers to enroll and partic-
    53  ipate through the utility, disenroll from the program  without  penalty,
    54  receive  dispatch  signals  and  other  communications from the utility,
    55  deliver performance measurement and verification data  to  the  utility,
    56  and  receive  program payments directly from the utility. Any provisions

        S. 9500                             6
 
     1  implementing this  subdivision  that  necessitate  the  installation  of
     2  communications or other equipment to enable direct participation via the
     3  utility  shall  apply to direct participant customers only and shall not
     4  be required of customers who participate via an aggregator or to custom-
     5  ers who do not participate in the program.
     6    (c)  Provisions  for  device eligibility which shall allow for partic-
     7  ipation of new and existing distributed energy resources on  a  non-dis-
     8  criminatory basis.
     9    (d)  Distributed energy resource deployment incentives through upfront
    10  payments as follows:
    11    (i) Battery rider participants shall be eligible  to  receive  upfront
    12  payments  through  the  energy storage incentive program administered by
    13  the New York  state  energy  research  and  development  authority,  its
    14  successor  program,  and  such  other  programs as may be available. The
    15  commission shall consult  and  work  with  the  New  York  state  energy
    16  research  and  development  authority  to provide low-to-moderate income
    17  customers and customers located in disadvantaged  communities  a  higher
    18  upfront  payment  value. Customers receiving such upfront payments shall
    19  be subject to conditions  established  by  the  New  York  state  energy
    20  research and development authority.
    21    (ii) All program participants shall be eligible to receive federal and
    22  other  state  incentives,  whether  in the form of upfront payments, tax
    23  credits, rebates or otherwise,  in  addition  to  the  upfront  payments
    24  provided in subparagraph (i) of this paragraph and the performance-based
    25  compensation provided in paragraph (e) of this subdivision. Where possi-
    26  ble,  the  commission  shall  coordinate  with the New York state energy
    27  research and development authority and other state and federal  agencies
    28  to  determine  the value of upfront payments and support customer access
    29  to such payments, including higher upfront payments for  low-to-moderate
    30  income customers and customers located in disadvantaged communities.
    31    (e) Program participation compensation through performance payments as
    32  follows:
    33    (i)  The  commission  shall  approve performance payment rates for the
    34  system peak load reduction service in the form of a dollar per  kilowatt
    35  value that is no lower than the sum of the capacity value and the demand
    36  reduction  value using the most recent information for such value compo-
    37  nents as provided  in  the  commission's  value  of  distributed  energy
    38  resources  proceeding,  case  no. 15-E-0751 or any successor proceeding,
    39  for each utility.
    40    (ii) The  commission  shall  approve  performance  payment  rates  for
    41  resources  providing  locational system relief services in the form of a
    42  dollar per kilowatt value no lower than  the  locational  system  relief
    43  value  using  the  most  recent information provided in the commission's
    44  value of distributed energy resources proceeding, case no. 15-E-0751  or
    45  any successor proceeding.
    46    (iii)  For a period of no less than four years from the effective date
    47  of this article, the demand reduction value for establishing the  system
    48  peak load reduction service performance payment rate shall be calculated
    49  based  on  the  system-wide  average  of  a utility's long-run, non-zero
    50  marginal cost of service, inclusive of all substation  areas  with  non-
    51  zero costs.
    52    (iv)  For  a period of no less than four years from the effective date
    53  of this article, the locational system relief value for establishing the
    54  locational system relief  service  performance  payment  rate  shall  be
    55  calculated based on a single level of locational system relief value for
    56  each  utility, reflecting the threshold level at which a utility's costs

        S. 9500                             7
 
     1  are significantly higher than costs on average on a  system-wide  basis.
     2  The  locational  system  relief  value  shall relate to no less than ten
     3  percent of a company's service areas for no less than  five  years  from
     4  the effective date of this article.
     5    (v) The commission shall utilize the demand reduction value, location-
     6  al  system  relief  value,  and  other values calculated pursuant to the
     7  commission's value of distributed energy resources proceeding, case  no.
     8  15-E-0751, or any successor proceeding, and such other related valuation
     9  considerations  to  establish  performance  payment rates, or such other
    10  compensation rates as the commission determines appropriate,  for  other
    11  grid  service offerings approved under the program other than the system
    12  peak reduction service and locational  system  peak  reduction  service,
    13  provided that such rates reflect fair value for the service provided.
    14    (vi)  Participants shall receive the performance payment rate approved
    15  for a grid service that is applicable at the time of  enrollment  for  a
    16  period  of  five  years.  After such five-year period, a participant may
    17  reenroll in the program at the then applicable rate for subsequent five-
    18  year terms.
    19    (vii) Participants shall be eligible to provide multiple grid services
    20  under multiple technology riders and receive compensation for each  grid
    21  service  pursuant  to each rider; provided, however, that the grid value
    22  delivered under one service is incremental to that provided under anoth-
    23  er service.
    24    (viii) Customers shall have the option to receive upfront payments and
    25  performance payments directly or to assign such payments to a third-par-
    26  ty.
    27    (ix) Performance payments shall be made by a utility to the applicable
    28  customer or third-party designated by the customer no less than once per
    29  year, but may be made more frequently, as approved by the commission.  A
    30  utility  shall  provide  performance  payments in the form of a check or
    31  electronic transfer of funds,  such  as  direct  deposit  or  other  ACH
    32  payment.
    33    (x) The commission shall periodically review performance payment rates
    34  in  relation  to  a utility's performance in achieving the participation
    35  targets established in section two hundred forty-three of this article.
    36    (f) Provisions to measure device performance, where:
    37    (i) Battery performance shall be measured directly  at  the  inverter;
    38  and
    39    (ii)  Non-battery  and  electric vehicle technology performance may be
    40  measured directly at the device or through such other  methodologies  as
    41  the commission may approve.
    42    (g)  Performance  payment compensation calculations and methodologies,
    43  where:
    44    (i)  System  peak  load  reduction  service  and  locational  services
    45  provided  under a battery rider shall be compensated based on the appli-
    46  cable  performance  payment  rate  multiplied  by  the  average  battery
    47  performance  as  measured  at  the  inverter during grid events over the
    48  course of the applicable measurement period. The  commission  may  adopt
    49  the  same  or  alternative  methodologies  to calculate compensation for
    50  other grid services offered under a  battery  rider  as  the  commission
    51  deems appropriate.
    52    (ii)  The  commission shall provide methodologies to calculate compen-
    53  sation for grid services offered under non-battery and electric  vehicle
    54  riders  taking  into account the ability to directly measure performance
    55  from the respective eligible technologies, costs of facilitating  direct
    56  measurement, and related considerations.

        S. 9500                             8
 
     1    (h)  A  utility may not assess penalties under this program; provided,
     2  however, that the commission may approve reasonable mechanisms to disen-
     3  roll participants for continued non-performance.
     4    (i)  Provisions allowing customers to co-participate in other programs
     5  and provide multiple grid services  across  riders  within  the  virtual
     6  power plant program, where:
     7    (i)  Customers  may  co-participate  in  the  net  metering,  value of
     8  distributed energy resources, and any other  applicable  interconnection
     9  tariff  approved  by the commission. Net metering customers shall not be
    10  required to transition to a value of  distributed  energy  resources  or
    11  other  non-net  metering  interconnection  tariff  to participate in the
    12  program.
    13    (ii) Customers may co-participate in one or more  program  riders  and
    14  provide  multiple grid services within each rider. Customers may partic-
    15  ipate in other grid service programs outside  the  virtual  power  plant
    16  program,  including wholesale market programs where otherwise permitted,
    17  so long as such value is distinct from that provided under  the  virtual
    18  power plant program.
    19    3.  The  following  additional  terms shall apply to the virtual power
    20  plant program:
    21    (a) Participating aggregators shall make customer performance data and
    22  related customer specific information available  to  the  customer  upon
    23  request  for  visibility  into  device  performance  under  the program.
    24  Aggregators shall provide a clear and prominently displayed statement on
    25  the application form and customer portal that such information is avail-
    26  able upon request. Aggregators shall include reasonable terms and condi-
    27  tions for customers to  disenroll  from  the  program  without  penalty;
    28  provided,  however,  that  aggregators  may  include reasonable terms to
    29  recoup monies from the customer that the aggregator is obligated to  pay
    30  back  to the New York state energy research and development authority or
    31  other entities as a result of a customer breach of commitment.
    32    (b) The commission may adopt other reasonable requirements for partic-
    33  ipation consistent with this subdivision; provided, however, that colla-
    34  teral or other financial commitments from aggregators or direct  partic-
    35  ipants shall not be required as a condition for participation.
    36    (c)  Utility-owned  distributed energy resources shall not be eligible
    37  to participate in the program. Utilities and utility affiliates may  not
    38  be aggregators.
    39    (d)  Utilities  shall  provide  non-discriminatory  access to customer
    40  data, hosting capacity data, and other  grid  data  to  facilitate:  (i)
    41  program enrollment; (ii) identification of grid support needs; and (iii)
    42  other  program  participation  considerations for customers, distributed
    43  energy resource developers and aggregators. No later than one year after
    44  the effective date of this article the commission shall promulgate rules
    45  allowing customers timely data sharing and third-party  access  to  grid
    46  data,  provided  that  such  rules shall not place undue burdens on such
    47  access.
    48    (e) Utilities  may  engage  third-party  distributed  energy  resource
    49  management system providers for program administration and other program
    50  support.
    51    (f) Each electric corporation shall take all necessary steps to facil-
    52  itate  and  streamline  the  processes  required for virtual power plant
    53  participation. Such efforts shall include, but not be limited to, reduc-
    54  ing administrative barriers and  transaction  costs  for  virtual  power
    55  plant  participants  and adopting standardized processes to simplify and
    56  ensure timely: (i) interconnection;  (ii)  data  sharing  and  automated

        S. 9500                             9
 
     1  system  integration  with  third-party aggregators; (iii) administrative
     2  and logistical coordination for mass-market enrollment; (iv) performance
     3  verification and payment settlement; and (v) such other measures as  the
     4  commission may direct.
     5    §  242.  Cost  recovery.  1.  Utilities may recover prudently incurred
     6  costs to facilitate administration and implementation of a virtual power
     7  plant program established pursuant to this article,  including  but  not
     8  limited  to  distributed  energy resource management system provider and
     9  other service  contract  costs,  operations  and  maintenance  expenses,
    10  information technology costs, and such other costs, expenses and invest-
    11  ments the commission finds necessary and prudent for the development and
    12  implementation of the program.
    13    2.  Utilities may recover the cost of program payments made to partic-
    14  ipants through cost recovery mechanisms approved by the commission.
    15    3. The commission may, at its discretion, allow a reasonable  rate  of
    16  return  on costs approved pursuant to this section. The commission shall
    17  take any such allowance into account  when  developing  the  performance
    18  incentive  structure pursuant to section two hundred forty-three of this
    19  article.
    20    § 243. Program targets and performance  incentive  mechanisms.  1.  No
    21  later  than  one  year  after  the  effective  date of this article, the
    22  commission shall, after  notice  and  opportunity  for  public  comment,
    23  establish  system  peak load reduction targets and performance incentive
    24  mechanisms for a virtual power plant program for each utility and  guid-
    25  ance  to  ensure  robust  initial  participant  engagement and growth of
    26  virtual power plant programs. Each such target shall: (a) be established
    27  for a minimum period of ten years; (b) include increasing annual  bench-
    28  marks;  and (c) be structured as a percentage of a utility system's peak
    29  demand to ensure the program scales dynamically with load growth.
    30    2. The commission shall adopt  performance  incentive  mechanisms  for
    31  achieving  or  exceeding  the  targets  established for each year of the
    32  performance period. The commission may include as part of  the  perform-
    33  ance incentive mechanism: (a) performance metrics; (b) publicly-accessi-
    34  ble data dashboards, scorecards, and other tracking tools; (c) financial
    35  incentives  and  financial  penalties  for  failure  to meet performance
    36  targets; and (d) such other mechanisms appropriate to track  performance
    37  and  create  financial  incentive  structures to motivate the utility to
    38  achieve performance targets.
    39    3. The commission shall develop program  performance  incentive  mech-
    40  anisms for additional grid services as the commission deems appropriate.
    41    §  244.  Reporting. Each utility shall file an annual report at a date
    42  determined by the commission that shall include, at minimum:
    43    1. the total participants enrolled in each virtual power plant program
    44  rider broken out by technology type, customer class, and aggregator  vs.
    45  direct  participants for each grid service offered in the prior calendar
    46  year;
    47    2. estimated cost reductions as a result of the  virtual  power  plant
    48  program and how such reductions are reflected in customer bill savings;
    49    3.  recommendations  to  increase  participation  in the virtual power
    50  plant program; and
    51    4. such other information as the commission may require.
    52    § 4. This act shall take effect immediately.