Ensures that construction and fabrication done off of a public work site for specific use only in a public work project be compensated at the prevailing wage rate.
STATE OF NEW YORK
________________________________________________________________________
8494--A
2021-2022 Regular Sessions
IN ASSEMBLY
November 17, 2021
___________
Introduced by M. of A. BRONSON -- read once and referred to the Commit-
tee on Labor -- recommitted to the Committee on Labor in accordance
with Assembly Rule 3, sec. 2 -- committee discharged, bill amended,
ordered reprinted as amended and recommitted to said committee
AN ACT to amend the labor law, in relation to inclusion of certain off-
site custom fabrication as public work for the purposes of payment of
prevailing wage
The People of the State of New York, represented in Senate and Assem-bly, do enact as follows:
1 Section 1. Legislative findings and intent. The legislature finds and
2 declares that the prevailing wage law was established to provide fair
3 and equitable working conditions, wages and supplementary benefits for
4 persons employed on public works construction projects.
5 The legislature further finds and declares that there are growing
6 number of instances where materials are fabricated off the public work
7 job site either to meet the unique specifications of the project subject
8 to a public work contract or for the contractor's convenience.
9 The legislature further finds and declares that in many instances the
10 prevailing wage is not paid to persons involved in off-site fabrication
11 of materials which are used specifically for public works projects.
12 It is the intent of the legislature that construction and fabrication
13 done off the public work site for specific use only in public work
14 projects be compensated at the prevailing wage rate.
15 § 2. Subdivision 3 of section 220 of the labor law is amended by
16 adding a new paragraph (f) to read as follows:
17 (f) For the purposes of this subdivision contractors or subcontractors
18 engaged in custom fabrication shall not be regarded as material suppli-
19 ers. For the purposes of this subdivision, a legal day's work for which
20 the prevailing rate of wages shall be paid to laborers, workers and
21 mechanics shall include custom fabrication whether or not the custom
22 fabrication is done on the public work site. It shall be a condition of
EXPLANATION--Matter in italics (underscored) is new; matter in brackets
[] is old law to be omitted.
LBD13465-02-2
A. 8494--A 2
1 the contract concerning such off-site custom fabrication work that the
2 contractor or employer awarded the public work contract shall covenant
3 to pay the on-site prevailing wage of the public work project. Each
4 contractor who employs workers off-site on a public work project shall
5 maintain certified payrolls and provide such payrolls, with original
6 certifications, to the contracting agency at least once every thirty
7 days. For the purposes of this subdivision the term "custom fabri-
8 cation" shall include, but not be limited to, the fabrication of exteri-
9 or or interior wall panel systems, the fabrication of woodwork, cases,
10 cabinets or counters and the fabrication of electrical, plumbing, heat-
11 ing, cooling, ventilation or exhaust duct systems, and mechanical insu-
12 lation solely and specifically designed and engineered for installation
13 in the construction, repair or renovation of a building which is the
14 subject of a contract to which the state, a municipal corporation, a
15 public benefit corporation or a commission appointed pursuant to law is
16 a party.
17 § 3. This act shall take effect on the sixtieth day after it shall
18 have become a law and shall apply only to those contracts put out to bid
19 on or after such effective date.