S00802 Summary:

BILL NOS00802A
 
SAME ASSAME AS UNI. A02347-A
 
SPONSORBRESLIN
 
COSPNSRHUNTLEY, SCHNEIDERMAN, STACHOWSKI, STAVISKY, THOMPSON
 
MLTSPNSR
 
Amd S139-f, St Fin L; amd S106-b, Gen Muni L
 
Provides for release of subcontractor's retainage held by a public owner or contractor sixty days after substantial completion of work.
Go to top    

S00802 Actions:

BILL NOS00802A
 
01/15/2009REFERRED TO FINANCE
10/14/2009AMEND AND RECOMMIT TO FINANCE
10/14/2009PRINT NUMBER 802A
01/06/2010REFERRED TO FINANCE
Go to top

S00802 Floor Votes:

There are no votes for this bill in this legislative session.
Go to top

S00802 Text:



 
                STATE OF NEW YORK
        ________________________________________________________________________
 
            S. 802--A                                             A. 2347--A
 
                               2009-2010 Regular Sessions
 
                SENATE - ASSEMBLY
 
                                    January 15, 2009
                                       ___________
 
        IN  SENATE  --  Introduced  by  Sens.  BRESLIN,  HUNTLEY,  SCHNEIDERMAN,
          STACHOWSKI, STAVISKY, THOMPSON -- read twice and ordered printed,  and
          when  printed to be committed to the Committee on Finance -- committee
          discharged, bill amended, ordered reprinted as amended and recommitted
          to said committee
 

        IN ASSEMBLY -- Introduced by M. of A. CUSICK, GABRYSZAK -- read once and
          referred to the Committee  on  Governmental  Operations  --  committee
          discharged, bill amended, ordered reprinted as amended and recommitted
          to said committee
 
        AN  ACT to amend the state finance law and the general municipal law, in
          relation to release of subcontractor's retainage
 
          The People of the State of New York, represented in Senate and  Assem-
        bly, do enact as follows:
 
     1    Section 1. Subdivision 2 of section 139-f of the state finance law, as
     2  amended  by  section 16 of part MM of chapter 57 of the laws of 2008, is
     3  amended to read as follows:
     4    2. Payment by contractors to  subcontractors.  Within  seven  calendar
     5  days of the receipt of any payment from the public owner, the contractor

     6  shall  pay  each of his subcontractors and materialmen the proceeds from
     7  the payment representing the value of the work performed and/or  materi-
     8  als furnished by the subcontractor and/or materialman and reflecting the
     9  percentage  of  the  subcontractor's work completed or the materialman's
    10  material supplied in the requisition approved by  the  owner  and  based
    11  upon  the  actual  value  of  the  subcontract or purchase order less an
    12  amount necessary to satisfy any claims, liens or judgments  against  the
    13  subcontractor or materialman which have not been suitably discharged and
    14  less any retained amount as hereafter described. Failure by the contrac-
    15  tor  to  pay any subcontractor or materialman within seven calendar days
    16  of the receipt of any payment from the public owner shall result in  the
    17  commencement  and accrual of interest on amounts due to such subcontrac-
 

         EXPLANATION--Matter in italics (underscored) is new; matter in brackets
                              [ ] is old law to be omitted.
                                                                   LBD00274-03-9

        S. 802--A                           2                         A. 2347--A
 
     1  tor or materialman for the  period  beginning  on  the  day  immediately
     2  following the expiration of such seven calendar day period and ending on
     3  the  date on which payment is made by the contractor to such subcontrac-
     4  tor or materialman. Such interest payment shall be the sole responsibil-
     5  ity  of  the  contractor,  and  shall be paid at the rate of interest in
     6  effect on the date payment is made by the contractor.    Notwithstanding
     7  any  other  provision of law to the contrary, interest shall be computed

     8  at the rate established in paragraph (b) of subdivision one  of  section
     9  seven  hundred  fifty-six-b  of the general business law. The contractor
    10  shall retain not more than five  per  centum  of  each  payment  to  the
    11  subcontractor  and/or  materialman except that the contractor may retain
    12  in excess of five per centum but not more than ten per  centum  of  each
    13  payment  to  the  subcontractor  provided  that prior to entering into a
    14  subcontract with the contractor, the subcontractor is unable or  unwill-
    15  ing to provide a performance bond and a labor and material bond, both in
    16  the  full  amount  of the subcontract, at the request of the contractor.
    17  However, the contractor shall retain nothing from those payments repres-
    18  enting proceeds owed  the  subcontractor  and/or  materialman  from  the
    19  public  owner's  payments to the contractor for the remaining amounts of

    20  the contract balance as provided in subdivision one of this section.  If
    21  the  contractor  has  failed  to submit a requisition for payment of the
    22  remaining amounts of the contract balance within ninety days of substan-
    23  tial completion as provided in subdivision one of this section, then any
    24  clause in the subcontract between the contractor and  the  subcontractor
    25  or  materialman  which  states  that  payment  by the contractor to such
    26  subcontractor or materialman is contingent upon payment by the owner  to
    27  the  contractor  shall  be deemed invalid. Within seven calendar days of
    28  the receipt of payment from the  contractor,  the  subcontractor  and/or
    29  materialman  shall pay each of his subcontractors and materialmen in the
    30  same manner as the contractor  has  paid  the  subcontractor,  including
    31  interest  as herein provided above. Nothing provided herein shall create

    32  any obligation on the part of the public owner to pay or to see  to  the
    33  payment  of  any  moneys  to  any  subcontractor or materialman from any
    34  contractor nor shall  anything  provided  herein  serve  to  create  any
    35  relationship in contract or otherwise, implied or expressed, between the
    36  subcontractor  or materialman and the public owner.  Notwithstanding any
    37  other provision of this section or other law, any retainage  held  by  a
    38  public  owner or contractor representing retainage for a subcontractor's
    39  work shall be released, less an amount necessary to satisfy any  claims,
    40  liens  or  judgments against the subcontractor or materialman which have
    41  not been suitably discharged and less an amount necessary to satisfy any
    42  charges for unfinished punch list items, no later than sixty  days  from

    43  the completion and acceptance by the public owner of the subcontractor's
    44  work.
    45    §  2.  Subdivision 2 of section 106-b of the general municipal law, as
    46  amended by section 15 of part MM of chapter 57 of the laws of  2008,  is
    47  amended to read as follows:
    48    2.  Payment  by  contractors  to subcontractors. Within seven calendar
    49  days of the receipt of any payment from the public owner, the contractor
    50  shall pay each of his subcontractors and materialmen the  proceeds  from
    51  the  payment representing the value of the work performed and/or materi-
    52  als furnished by the subcontractor and/or materialman and reflecting the
    53  percentage of the subcontractor's work completed  or  the  materialman's
    54  material  supplied  in  the  requisition approved by the owner and based
    55  upon the actual value of the  subcontract  or  purchase  order  less  an

    56  amount  necessary  to satisfy any claims, liens or judgments against the

        S. 802--A                           3                         A. 2347--A
 
     1  subcontractor or materialman which have not been suitably discharged and
     2  less any retained amount as hereafter described. Failure by the contrac-
     3  tor to make any payment, including any remaining amounts of the contract
     4  balance  as  hereinafter  described, to any subcontractor or materialman
     5  within seven calendar days of the receipt of any payment from the public
     6  owner shall result in  the  commencement  and  accrual  of  interest  on
     7  amounts  due  to such subcontractor or materialman for the period begin-
     8  ning on the day immediately  following  the  expiration  of  such  seven
     9  calendar  day  period and ending on the date on which payment is made by

    10  the contractor to such subcontractor or materialman. Such interest shall
    11  be the sole responsibility of the contractor, and shall be paid  at  the
    12  rate  of  interest in effect on the date payment is made by the contrac-
    13  tor. Notwithstanding any other provision of law to the contrary,  inter-
    14  est shall be computed at the rate established in paragraph (b) of subdi-
    15  vision  one of section seven hundred fifty-six-b of the general business
    16  law. The contractor shall retain not more than five per centum  of  each
    17  payment to the subcontractor and/or materialman except that the contrac-
    18  tor  may  retain  in excess of five per centum but not more than ten per
    19  centum of each payment to  the  subcontractor  provided  that  prior  to
    20  entering  into  a  subcontract with the contractor, the subcontractor is
    21  unable or unwilling to provide a performance bond and a labor and  mate-

    22  rial  bond  both in the full amount of the subcontract at the request of
    23  the contractor. However, the contractor shall retain nothing from  those
    24  payments representing proceeds owed the subcontractor and/or materialman
    25  from  the  public  owner's  payments to the contractor for the remaining
    26  amounts of the contract balance as provided in subdivision one  of  this
    27  section.  If  the  contractor  has  failed  to  submit a requisition for
    28  payment of the remaining amounts of the contract balance  within  ninety
    29  days  of  substantial  completion as provided in subdivision one of this
    30  section, then any clause in the subcontract between the  contractor  and
    31  the  subcontractor  or  materialman  which  states  that  payment by the
    32  contractor to such  subcontractor  or  materialman  is  contingent  upon
    33  payment  by  the owner to the contractor shall be deemed invalid. Within

    34  seven calendar days of the receipt of payment from the  contractor,  the
    35  subcontractor  and/or  materialman  shall pay each of his subcontractors
    36  and materialmen in the same  manner  as  the  contractor  has  paid  the
    37  subcontractor,  including  interest  as herein provided above.   Nothing
    38  provided herein shall create any obligation on the part  of  the  public
    39  owner to pay or to see to the payment of any moneys to any subcontractor
    40  or  materialman  from  any contractor nor shall anything provided herein
    41  serve to create any relationship in contract or  otherwise,  implied  or
    42  expressed,  between  the  subcontractor  or  materialman  and the public
    43  owner.  Notwithstanding any other provision of  this  section  or  other
    44  law,  any  retainage  held  by a public owner or contractor representing

    45  retainage for a subcontractor's work shall be released, less  an  amount
    46  necessary  to satisfy any claims, liens or judgments against the subcon-
    47  tractor or materialman which have not been suitably discharged and  less
    48  an  amount  necessary  to  satisfy any charges for unfinished punch list
    49  items, no later than sixty days from the completion  and  acceptance  by
    50  the public owner of the subcontractor's work.
    51    §  3.  This  act  shall take effect immediately and shall apply to all
    52  contracts entered into on or after its effective date.