Establishes a highway and depot charging needs evaluation to assist in achieving targets set forth by the climate leadership and community protection act, zero-emissions vehicle sales target and regulations, including the advanced clean truck, advanced clean cars II rules and the zero-emissions school bus mandate.
STATE OF NEW YORK
________________________________________________________________________
4830--C
2023-2024 Regular Sessions
IN SENATE
February 15, 2023
___________
Introduced by Sens. KENNEDY, COMRIE, COONEY, GOUNARDES, HARCKHAM, HOYL-
MAN-SIGAL, MAYER, PARKER -- read twice and ordered printed, and when
printed to be committed to the Committee on Corporations, Authorities
and Commissions -- committee discharged, bill amended, ordered
reprinted as amended and recommitted to said committee -- committee
discharged, bill amended, ordered reprinted as amended and recommitted
to said committee -- committee discharged, bill amended, ordered
reprinted as amended and recommitted to said committee
AN ACT to amend the public authorities law, in relation to conducting a
highway and depot charging needs evaluation
The People of the State of New York, represented in Senate and Assem-bly, do enact as follows:
1 Section 1. Legislative findings. In order to achieve targets set forth
2 by the climate leadership and community protection act, zero-emissions
3 vehicle sales target and regulations, including the advanced clean truck
4 and advanced clean cars II rules, zero-emissions school bus mandate, and
5 other relevant goals, the interests of the people of the state would be
6 served by:
7 1. Coordinating efforts to plan for electric vehicle fast-charging
8 deployment on New York's highways;
9 2. Identifying priority sites for the deployment of fast chargers
10 along New York's highways, estimating future charging demand at these
11 sites for all vehicle classes, and identifying necessary electric grid
12 transmission and distribution infrastructure and interconnection
13 upgrades at these sites;
14 3. Expediting electric grid transmission and distribution infrastruc-
15 ture and interconnection upgrades at sites controlled by the New York
16 state thruway authority, sufficient to future-proof thruway sites for
17 accelerated fast charger deployment to serve light duty, medium duty and
18 heavy duty vehicles; and
EXPLANATION--Matter in italics (underscored) is new; matter in brackets
[] is old law to be omitted.
LBD09078-10-3
S. 4830--C 2
1 4. Identifying additional high priority areas for the deployment of
2 charging for medium and heavy duty vehicles, such as school buses, tran-
3 sit buses, and other light, medium and heavy duty commercial fleet
4 depots, including taxi and ride-share vehicle fleets, and removing
5 barriers to charging deployment, including electric infrastructure
6 constraints.
7 5. Identifying additional priority areas for deployment of charging
8 infrastructure designed to support building of charging in densely popu-
9 lated urban areas where access to charging is currently or may be limit-
10 ed.
11 § 2. The public authorities law is amended by adding a new section
12 1885 to read as follows:
13 § 1885. Highway and depot charging needs evaluation. 1. Within nine
14 months of the effective date of this section, and every three years
15 thereafter, the authority, in consultation with the department of trans-
16 portation, the department of motor vehicles, the New York state thruway
17 authority, the New York power authority, the Long Island power authori-
18 ty, the department of environmental conservation, the electric distrib-
19 ution and local transmission utilities, the New York Association for
20 Pupil Transportation, and freight logistics experts shall conduct a
21 needs evaluation to:
22 (a) consider planning by the department of transportation for fast
23 charger deployment along alternative fuel corridors and major freight
24 corridors;
25 (b) identify the number and location of fast chargers along priority
26 highway corridors and major freight corridors, including fast chargers
27 currently in operation and in development;
28 (c) estimate future need for fast charger deployment along priority
29 highway and major freight corridors for the purposes of (i) facilitating
30 the cost-effective and timely achievement of mandates under (1) article
31 seventy-five of the environmental conservation law, (2) section
32 19-0306-b of the environmental conservation law regarding zero-emissions
33 vehicle sales targets, (3) rules and regulations for zero-emissions
34 vehicles adopted by the commissioner of environmental conservation, and
35 (4) other relevant and applicable federal and state rules or regulations
36 or local goals to reduce transportation sector emissions; and (ii)
37 supporting electric vehicle adoption by consumers and fleet operators;
38 (d) identify the number and location of highway charging hubs, includ-
39 ing but not limited to thruway charging hubs and freight charging hubs,
40 currently in operation and in development along priority highway and
41 major freight corridors;
42 (e) estimate total charging capacity required to serve light duty,
43 medium duty, and heavy duty electric vehicles at each highway and
44 freight charging hub through at least the year two thousand fifty;
45 (f) identify, to the extent practicable, the number and location of
46 commercial and public fleet vehicles in operation, including their body
47 type, fuel type, model year, zip code, and other relevant information
48 needed to forecast the number and location of zero-emissions vehicles,
49 per state policy;
50 (g) identify the number and location of fleet charging zones;
51 (h) estimate future need for charging deployment and charging capacity
52 in the fleet charging zones, sufficient to satisfy the targets and regu-
53 lations identified in paragraph (c) of this subdivision;
54 (i) examine ways to optimize fast charger deployment among the highway
55 charging hubs, the freight charging hubs, and all such charging hubs,
56 and charging development among the fleet charging zones to reduce the
S. 4830--C 3
1 cost of interconnection, if deemed necessary, and electric distribution
2 and local transmission upgrades while serving projected vehicle traffic
3 volumes;
4 (j) analyze and asses the total potential costs associated with any
5 identified need;
6 (k) analyze and assess federal or state funding opportunities to mini-
7 mize such costs to rate payers; and
8 (l) identify the number and location of critical public charging sites
9 and estimate future need for charging deployment and charging capacity
10 for critical public charging sites.
11 2. The authority shall develop a stakeholder engagement process to
12 raise consumer awareness and education across the state and solicit
13 feedback from the public, local government, representatives or residents
14 of environmental justice or disadvantaged communities, electric vehicle
15 manufacturers, electric vehicle supply equipment manufacturers, fleet
16 operators, school district transportation directors and others on the
17 highway and depot charging needs evaluation. To the extent practicable
18 and consistent with applicable timelines, the authority may coordinate
19 the highway and depot charging needs evaluation stakeholder input proc-
20 ess with the process set forth in section eighteen hundred eighty-four
21 of this article.
22 3. The needs evaluation shall be made publicly available on the
23 authority's website.
24 4. When conducting the needs evaluation, the following locations shall
25 be considered for designation as highway and/or freight charging hubs:
26 (a) All thruway charging hubs.
27 (b) Additional sites or geographic areas based on (i) eligibility for
28 federal, state, or other funding opportunities, including but not limit-
29 ed to needs identified through the NEVI formula program planning proc-
30 ess, (ii) proximity to electric transmission infrastructure, (iii)
31 projected vehicle traffic, (iv) charging network coverage, (v) inter-
32 state and intrastate commerce, (vi) benefits to environmental justice
33 and disadvantaged communities, (vii) benefits of increased charging
34 accessibility in host communities, (viii) real property ownership or
35 control of potential sites, (ix) relevant commitments from site and/or
36 charging operators, and (x) other factors deemed relevant for the devel-
37 opment and successful implementation of the highway charging needs eval-
38 uation.
39 (c) Locations within one mile of the priority highway corridors,
40 spaced no more than fifty miles apart along the priority highway corri-
41 dors and reasonably accessible regardless of direction of travel.
42 (d) Privately operated sites which are open to the public or multiple
43 commercial entities as eligible for designation as a highway charging
44 hub or freight charging hub, subject to reasonable restrictions.
45 (e) A single highway or freight charging hub comprised of multiple
46 charging service areas within a reasonable distance from one another.
47 5. When conducting the needs evaluation, the following geographic area
48 criteria shall be considered when determining designations as fleet
49 charging zones:
50 (a) total number of commercial and public fleet vehicles in operation
51 and/or total number of fleet operators in the geographic area,
52 (b) projected vehicle traffic in the geographic area,
53 (c) benefits to public fleets, such as school bus operators,
54 (d) benefits to environmental justice and disadvantaged communities,
55 (e) relevant commitments from fleet and/or site operators to install
56 charging equipment,
S. 4830--C 4
1 (f) available capacity on the electric distribution and local trans-
2 mission network to serve vehicle chargers,
3 (g) ensuring equitable coverage and access to fleet charging through-
4 out the state, and
5 (h) sites where private or public fleet vehicles are regularly parked,
6 maintained, or otherwise dispatched for service, including school bus
7 garages.
8 6. As used in this section, the following terms shall have the follow-
9 ing meanings:
10 (a) "Alternative fuel corridors" shall mean highways designated within
11 the state pursuant to the national electric vehicle infrastructure
12 formula program under 23 U.S.C. 151 and previously designated under the
13 federal Fixing America's Surface Transportation Act of 2015.
14 (b) "Charging needs evaluation" shall mean the highway and depot
15 charging needs evaluation.
16 (c) "Critical public charging site" shall mean a priority site for the
17 deployment of charging infrastructure designed to support buildout of
18 charging in densely populated urban areas where access to charging may
19 be limited.
20 (d) "Fast charger" shall mean a direct current electric vehicle charg-
21 ing port which can charge at a level of at least one hundred fifty kilo-
22 watts.
23 (e) "Fleet charging zone" shall mean a priority geographic area for
24 the deployment of charging infrastructure for public and commercial
25 fleet operators or owners, including school bus fleets, taxi and ride-
26 share vehicle fleets.
27 (f) "Freight charging hub" shall mean a priority site for the deploy-
28 ment of large scale, fast charging infrastructure, which has minimum
29 station power capability at or above six hundred kilowatts and supports
30 at least one hundred fifty kilowatts per port simultaneously across four
31 ports for charging. These sites may include highway charging hubs.
32 (g) "Highway and depot charging needs evaluation" shall mean the needs
33 evaluation developed pursuant to subdivision two of this section.
34 (h) "Highway charging hub" shall mean a priority site for the deploy-
35 ment of large scale, fast charging infrastructure, which has minimum
36 station power capability at or above six hundred kilowatts and supports
37 at least one hundred fifty kilowatts per port simultaneously across four
38 ports for charging. These sites shall include but are not limited to
39 thruway charging hubs.
40 (i) "Major freight corridor" shall mean segments of the freight trans-
41 portation network identified by the federal highway administration that
42 carry more than fifty million tons per year, including highway segments
43 that carry at least eight thousand five hundred trucks per day, addi-
44 tional highway segments and parallel rail lines that together carry at
45 least eight thousand five hundred truck, trailer-on-flatcar, and
46 container-on-flatcar payloads of typically high-value, time sensitive
47 cargo, and rail lines and waterways that carry fifty million tons in
48 bulk cargo per year.
49 (j) "NEVI" shall mean the national electric vehicle infrastructure
50 program established under the federal Infrastructure Investment and Jobs
51 Act of 2021.
52 (k) "Priority highway corridor" shall mean alternative fuel corridors
53 and other state and county highways identified in the charging needs
54 evaluation as appropriate to ensure sufficient and equitable charging
55 access throughout the state.
S. 4830--C 5
1 (l) "Thruway charging hubs" shall mean all highway service areas
2 controlled, leased, owned, or operated by the New York state thruway
3 authority.
4 § 3. This act shall take effect immediately.