S07478 Summary:

BILL NOS07478A
 
SAME ASSAME AS A09939-A
 
SPONSORHANNON
 
COSPNSR
 
MLTSPNSR
 
Amd S2802, Pub Health L
 
Establishes time limits for the consideration of applications for the construction of hospitals.
Go to top    

S07478 Actions:

BILL NOS07478A
 
05/15/2014REFERRED TO HEALTH
06/09/2014AMEND AND RECOMMIT TO HEALTH
06/09/2014PRINT NUMBER 7478A
06/17/2014COMMITTEE DISCHARGED AND COMMITTED TO RULES
06/17/2014ORDERED TO THIRD READING CAL.1478
06/17/2014PASSED SENATE
06/17/2014DELIVERED TO ASSEMBLY
06/17/2014referred to health
Go to top

S07478 Floor Votes:

There are no votes for this bill in this legislative session.
Go to top

S07478 Text:



 
                STATE OF NEW YORK
        ________________________________________________________________________
 
                                         7478--A
 
                    IN SENATE
 
                                      May 15, 2014
                                       ___________
 
        Introduced  by  Sen.  HANNON -- read twice and ordered printed, and when
          printed to be committed  to  the  Committee  on  Health  --  committee
          discharged, bill amended, ordered reprinted as amended and recommitted
          to said committee
 
        AN  ACT  to amend the public health law, in relation to applications for
          construction of hospitals
 

          The People of the State of New York, represented in Senate and  Assem-
        bly, do enact as follows:
 
     1    Section  1. Section 2802 of the public health law is amended by adding
     2  two new subdivisions 8 and 9 to read as follows:
     3    8. Notwithstanding any law, rule, or regulation to the contrary,  this
     4  subdivision  shall  apply  to  any application for construction required
     5  under this section with  the  exception  of  those  federally  qualified
     6  health  center  capital projects subject to section twenty-eight hundred
     7  seven-z of this article.
     8    (a) For an application requiring a limited or  administrative  review,
     9  within  ninety  calendar  days of the department deeming the application
    10  complete, the commissioner shall make a decision to  approve  or  disap-

    11  prove  the application. If the commissioner determines to disapprove the
    12  application, the basis for such disapproval shall be provided  in  writ-
    13  ing;  however,  disapproval  shall not be based on the incompleteness of
    14  the application. If the commissioner fails to take action to approve  or
    15  disapprove  the  application within ninety calendar days of the applica-
    16  tion being deemed complete, the application shall be deemed approved.
    17    (b) For an application requiring  full  review  by  the  council,  the
    18  application  shall  be  placed  on the next council agenda following the
    19  department deeming the application complete.
    20    (c) Where the commissioner or department  requires  the  applicant  to

    21  submit  information to satisfy a contingency for a construction project,
    22  the commissioner or department shall have thirty calendar days to review
    23  and approve or disapprove the submitted information. If the commissioner
    24  or department determines that the submitted information  is  incomplete,
    25  it  shall  so  notify the applicant in writing and provide the applicant
    26  with ten calendar days to correct the deficiency or  provide  additional
 
         EXPLANATION--Matter in italics (underscored) is new; matter in brackets
                              [ ] is old law to be omitted.
                                                                   LBD15126-02-4

        S. 7478--A                          2
 

     1  information.  If  the  commissioner  or  department  determines that the
     2  submitted information does not satisfy the contingency,  the  basis  for
     3  such  disapproval  shall  be  provided  in writing; however, disapproval
     4  shall  not  be  based  on  the incompleteness of the application. Within
     5  fifteen calendar days of complete satisfaction  of  a  contingency,  the
     6  commissioner  or  department shall transmit the final approval letter to
     7  the applicant.
     8    (d) The department shall develop expedited  pre-opening  survey  proc-
     9  esses for applications approved under this section, but under no circum-
    10  stances  shall pre-opening survey reviews be scheduled later than thirty
    11  calendar days after final approval, construction completion and  notifi-

    12  cation of such completion of the department.
    13    9.  With regard to any construction project requiring submission of an
    14  application pursuant to this section where the commissioner  has  deter-
    15  mined  that a written certification by an architect or engineer licensed
    16  pursuant to article one hundred forty-five or one hundred forty-seven of
    17  the education law that the project meets applicable regulations  of  the
    18  department  can  be  accepted,  the  submission by the applicant of such
    19  complete and fully executed certification  by  certified  or  registered
    20  mail  with  a return receipt signed by the department shall constitute a
    21  fulfillment of the certification requirement and  the  department  shall

    22  proceed with the processing of such application. Nothing in this section
    23  shall  be  construed  as  prohibiting  the  department  upon survey from
    24  requiring subsequent corrections to the project to meet  the  applicable
    25  regulations.
    26    § 2. This act shall take effect on the one hundred twentieth day after
    27  it shall have become a law.
Go to top