Requires for construction activities that require a state pollutant discharge elimination system permit owners and operators to submit a copy of the required public notice; requires each county receiving such notice to make such notice publicly available on its website.
Go to top    

S08171 Actions:

BILL NOS08171
 
01/10/2024REFERRED TO ENVIRONMENTAL CONSERVATION
01/16/20241ST REPORT CAL.134
01/17/20242ND REPORT CAL.
01/22/2024ADVANCED TO THIRD READING
02/13/2024PASSED SENATE
02/13/2024DELIVERED TO ASSEMBLY
02/13/2024referred to environmental conservation
Go to top

S08171 Committee Votes:

Go to top

S08171 Floor Votes:

There are no votes for this bill in this legislative session.
Go to top

S08171 Text:



 
                STATE OF NEW YORK
        ________________________________________________________________________
 
                                          8171
 
                    IN SENATE
 
                                    January 10, 2024
                                       ___________
 
        Introduced  by Sen. HARCKHAM -- read twice and ordered printed, and when
          printed to be committed to the Committee on Environmental Conservation
 
        AN ACT to amend the  environmental  conservation  law,  in  relation  to
          requiring  for  construction activities that require a state pollutant
          discharge elimination system permit owners and operators to  submit  a
          copy of the required public notice

          The  People of the State of New York, represented in Senate and Assem-
        bly, do enact as follows:
 
     1    Section 1. Subdivision 1  of  section  17-0805  of  the  environmental
     2  conservation  law  is  amended  by adding a new paragraph a-1 to read as
     3  follows:
     4    a-1. (i) For storm water from construction activities that requires  a
     5  SPDES  permit,  the owner or operator shall provide a copy of the public
     6  notice required by paragraph a of this  subdivision  to  the  county  or
     7  counties in which such construction activities take place, and all other
     8  counties, the waters of which may be affected.
     9    (ii) Each county receiving such notice shall make such notice publicly
    10  available on its website in a manner prescribed by the department.
    11    § 2. This act shall take effect on the one hundred eightieth day after
    12  it  shall have become a law. Effective immediately, the addition, amend-
    13  ment and/or repeal of  any rule or regulation necessary for  the  imple-
    14  mentation  of  this  act on its effective date are authorized to be made
    15  and completed on or before such effective date.
 
 
 
 